*Created schematic of Solenoid Assembly with Hydraulic Connectors in [https://docs.google.com/presentation/d/1SUUtXan2g-ZltK5WlgeAXnqHiHaWgqLzG8JlQRqrjkc/edit#slide=id.g1d984a886_017 google presentation]
*Created schematic of Solenoid Assembly with Hydraulic Connectors in [https://docs.google.com/presentation/d/1SUUtXan2g-ZltK5WlgeAXnqHiHaWgqLzG8JlQRqrjkc/edit#slide=id.g1d984a886_017 google presentation]
*Created [[Lasersaur_Exterior_Panel_Installation]] to document current status of Lasersaur exterior panel installation
*Created [[Lasersaur_Exterior_Panel_Installation]] to document current status of Lasersaur exterior panel installation
*Helped Organize workshop
*Disassembled solenoid valve assembly and began cleaning/degreasing components in preparation for reassembly


==Wed. 4 Jun. 2014==
==Wed. 4 Jun. 2014==

Revision as of 00:57, 6 June 2014

Thur. 5 Jun. 2014


Wed. 4 Jun. 2014

Tues. 3 Jun 2014

  • Documented problems encountered during Lasersaur Exterior Panel Installation
  • Started Workshop reorganize and fixed some power tool plugs and extension cord ends.
  • Worked with a team to reassemble the CEB Press. Learned it is important to have a CAD model that matches the actual model. Also good to replace nuts and washers onto corresponding bolts while disassembling in order to simplify reassembly.

Mon. 2 Jun 2014

Sat. 31 May 2014

  • Finalized prep for OSE
  • Installed software recommended in DPV Offer Letter