=Test-Driven Requirements= | |||
*Water, septic tank, outdoor water hydrant, external 200A breaker and connection point for downstream 200A circuit, internet line | |||
*Documentation of all line paths and burial depths | |||
*Direct connection from street breaker panel to MicroHouse | |||
*Use 0000 aluminum cable for power | |||
*Attend to crossing points of internet, and attend to location of deeper water lines | |||
*1" poly pipe for water | |||
*Power cable depth of 18" | |||
*Water line depth of 36" | |||
*Internet line depth of 18" | |||
*Water teed into Hablab, and teed off for MicroHouse 3 | |||
*Underground water fittings are buried directly using corrosion-free fittings | |||
*Leave provision for further extension of power grid from MicroHouse 3 |
Revision as of 16:41, 7 September 2014
Test-Driven Requirements
- Water, septic tank, outdoor water hydrant, external 200A breaker and connection point for downstream 200A circuit, internet line
- Documentation of all line paths and burial depths
- Direct connection from street breaker panel to MicroHouse
- Use 0000 aluminum cable for power
- Attend to crossing points of internet, and attend to location of deeper water lines
- 1" poly pipe for water
- Power cable depth of 18"
- Water line depth of 36"
- Internet line depth of 18"
- Water teed into Hablab, and teed off for MicroHouse 3
- Underground water fittings are buried directly using corrosion-free fittings
- Leave provision for further extension of power grid from MicroHouse 3