How to prevent bottlenecks - and allow a novice team to produce advanced design?
- We start with a Basic Diagram.
- We move on to Detailed Diagram outlining critical design features
- We include calculations
- We take it to CAD right away - cad up a design - and print a smaller scale item
- A tech lead provides design rationales and explanations - at the most granular level
- We outline Critical Challenges:
- Pulley desing
- Frame mounting detail
- Motor piece Minimum Detail
- Idler piece MVP
- Carriage piece MVP
- Coupling of motor to idler
- Coupling of motor to pulley
- 2-sided drive
- Scaling TB6600 to 2-4 motors by simple division from RAMPS - rapid prototype
- Carriage full scale motion prototyping
- Shaft preparation
- Bushing preparation
- 3D Printed acetal bushings