Cost of CEB Block: Difference between revisions

From Open Source Ecology
Jump to navigation Jump to search
Line 31: Line 31:
[https://docs.google.com/spreadsheets/d/1YyAIluT8FzHx8Vax9QNFAnIKrFmSQnEzdbSfeZMONt8/edit?folder=0ALpE5Y9PpJCXUk9PVA#gid=0 edit spreadsheet]
[https://docs.google.com/spreadsheets/d/1YyAIluT8FzHx8Vax9QNFAnIKrFmSQnEzdbSfeZMONt8/edit?folder=0ALpE5Y9PpJCXUk9PVA#gid=0 edit spreadsheet]


=Upload=
=Upload of Key Costs=
[[File:CEBblockcost.jpg|200px]]
[[File:CEBblockcost.jpg|200px]]

Revision as of 03:21, 9 January 2020

Commercial

  • $1 for unstabilized, $1.20 for stabilized - [1]

OSE Costs

  • Costs based on on-site soil availability
  • 6 block per minute machine - 8 hour shift - 1 gallon per hour for CEB, 0.5 gallon per hour for tractor, one gallon per hour for soil mixer, local clay soil, 10% cement stabilized
  • Total costs for 2880 block:
  1. 2.5 gal* 8=20 gal fuel = $50 at current gas prices
  2. Cement - $10 per bag for 100 block - 29 bags of cement - $290
  3. Labor - $25/hr for tractor operator, $15/hr for stacking block on pallets x2 - $440/day
  4. Water - 20 ml/block = 58 liters = 15 gallons at 2 cents - 30 cents in water
  5. Plastic wrap
  6. Pallets

Total costs -