Cost of CEB Block: Difference between revisions
Jump to navigation
Jump to search
No edit summary |
No edit summary |
||
Line 2: | Line 2: | ||
*$1 for unstabilized, $1.20 for stabilized - [http://www.midwestearthbuilders.com/BuildingInfo.html] | *$1 for unstabilized, $1.20 for stabilized - [http://www.midwestearthbuilders.com/BuildingInfo.html] | ||
=OSE | =OSE Costs= | ||
{{Hint|One scenario missing is soil digging, which adds 1.5 gallon per hour cost of fuel to the overall operation | {{Hint|One scenario missing is soil digging, which adds 1.5 gallon per hour cost of fuel to the overall operation.}} | ||
*Costs based on availability of on-site soil | *Costs based on availability of on-site soil | ||
* | *6 block per minute machine - 8 hour shift - 1 gallon per hour for CEB, 0.5 gallon per hour for tractor (25% duty cycle assuming nearby pile of soil that has already been dug), one gallon per hour for soil mixer, local clay soil, 10% cement stabilized | ||
*Total costs for 2880 block: | *Total costs for 2880 block: | ||
#2.5 gal* 8=20 gal fuel = $50 at current gas prices | #2.5 gal* 8=20 gal fuel = $50 at current gas prices | ||
# | #Cement - $10 per bag for 100 block - 29 bags of cement - $290 | ||
#Labor - $25/hr for tractor operator, $15/hr for stacking block on pallets x2 - $440/day | #Labor - $25/hr for tractor operator, $15/hr for stacking block on pallets x2 - $440/day | ||
#Water - 20 ml/block = 58 liters = 15 gallons at 2 cents - 30 cents in water | #Water - 20 ml/block = 58 liters = 15 gallons at 2 cents - 30 cents in water | ||
#Plastic wrap | #Plastic wrap | ||
#Pallets | #Pallets | ||
Line 38: | Line 34: | ||
=Upload of Key Costs= | =Upload of Key Costs= | ||
[[File:CEBblockcost.jpg|200px]] | [[File:CEBblockcost.jpg|200px]] | ||
Revision as of 17:58, 17 February 2020
Commercial
- $1 for unstabilized, $1.20 for stabilized - [1]
OSE Costs
Hint: One scenario missing is soil digging, which adds 1.5 gallon per hour cost of fuel to the overall operation.
- Costs based on availability of on-site soil
- 6 block per minute machine - 8 hour shift - 1 gallon per hour for CEB, 0.5 gallon per hour for tractor (25% duty cycle assuming nearby pile of soil that has already been dug), one gallon per hour for soil mixer, local clay soil, 10% cement stabilized
- Total costs for 2880 block:
- 2.5 gal* 8=20 gal fuel = $50 at current gas prices
- Cement - $10 per bag for 100 block - 29 bags of cement - $290
- Labor - $25/hr for tractor operator, $15/hr for stacking block on pallets x2 - $440/day
- Water - 20 ml/block = 58 liters = 15 gallons at 2 cents - 30 cents in water
- Plastic wrap
- Pallets
Total costs -