Seed Eco-Home Cost Structure: Difference between revisions

From Open Source Ecology
Jump to navigation Jump to search
No edit summary
Line 2: Line 2:
*1000 sf
*1000 sf
*2 bed, 2 bath
*2 bed, 2 bath
*Heat pump
*Heat pump, induction cooktop, and efficient water heater are standard options.
*6 kW PV option (saves $1000/year)
*6 kW PV option (saves $1000/year). See [[PV System Install Cost]].
 
*Attached carport


=Costs=
=Costs=

Revision as of 15:22, 12 May 2022

Features

  • 1000 sf
  • 2 bed, 2 bath
  • Heat pump, induction cooktop, and efficient water heater are standard options.
  • 6 kW PV option (saves $1000/year). See PV System Install Cost.
  • Attached carport

Costs

(these are subject to change without notice due to cost fluctuations, workflow requirements, legal requirements, engineering requirements, hidden commercial costs)

  • $50k materials. 6 kW PV option - $10k materials
  • Developer Profit Margin
  • Closing Costs - real estate commission, taxes, closing fees, selling concessions
  • Labor - 1000 hours at $50/hr for startup phase
  • Lot - from free to $85k average lot cost USA.