SEH in 5 Trailer Loads: Difference between revisions
Jump to navigation
Jump to search
No edit summary |
No edit summary |
||
Line 7: | Line 7: | ||
#Insulation + beadboard + flooring + interior trim | #Insulation + beadboard + flooring + interior trim | ||
#Landscaping, waste, water, electrical connection. | #Landscaping, waste, water, electrical connection. | ||
=Narrative= | |||
Get inverter and solar up as soon as possible so that we have power. For the 240V input, use a 240V feed from a small inverter or use small gen with [[120-240 Transformer]] |
Revision as of 22:03, 22 January 2023
Loads
- Foundation
- Floor 1 + subfloor + garage
- Floor 2 + roof + PV + House wrap
- Interior framing with MEP and Tubs + doors + exterior trim + siding
- Insulation + beadboard + flooring + interior trim
- Landscaping, waste, water, electrical connection.
Narrative
Get inverter and solar up as soon as possible so that we have power. For the 240V input, use a 240V feed from a small inverter or use small gen with 120-240 Transformer