Solar Fire at Factor e Farm: Difference between revisions

From Open Source Ecology
Jump to navigation Jump to search
m (adding wikilinks)
m (fixing redlink)
 
Line 4: Line 4:
#Factor e Team - shake down sourcing, prototype mirror assembly, and build foundation for solar concentrator - August
#Factor e Team - shake down sourcing, prototype mirror assembly, and build foundation for solar concentrator - August
#Eerik - organize automation team (Pivotal project tracking) for solar tracking mechanism
#Eerik - organize automation team (Pivotal project tracking) for solar tracking mechanism
#Produce [[steam engine]] with [[Mark Norton]] (by end of July for testing)
#Produce [[steam engine]] with [[User:Mjn|Mark Norton]] (by end of July for testing)


[[Category:Solar Fire]]
[[Category:Solar Fire]]
[[Category:Solar Concentrator]]
[[Category:Solar Concentrator]]

Latest revision as of 02:18, 3 June 2011

Project Plan for Solar Fire

  1. Produce full CAD documentation for the Solar Fire collector - June
  2. Produce detailed fabrication procedure and BOM for Solar Fire - July
  3. Factor e Team - shake down sourcing, prototype mirror assembly, and build foundation for solar concentrator - August
  4. Eerik - organize automation team (Pivotal project tracking) for solar tracking mechanism
  5. Produce steam engine with Mark Norton (by end of July for testing)