Crack Of Dawn Meetings: Difference between revisions

From Open Source Ecology
Jump to navigation Jump to search
No edit summary
Line 9: Line 9:
**Filter Assembly Instructions
**Filter Assembly Instructions
**Assembly and Weld!
**Assembly and Weld!
**Goal to finish power cubes by end of today.
*Whiteboards
*Whiteboards
*Bakers supply run.
*Bakers supply run.

Revision as of 21:54, 2 September 2011

Friday, September 02 (4:30)

  • Power Cubes almost done!
    • Finish leak testing on tanks
    • Checkoff on cuts
    • Frames all welded
    • Wiring Instructions
    • Battery Cables
    • Throttle Mounts
    • Filter Assembly Instructions
    • Assembly and Weld!
    • Goal to finish power cubes by end of today.
  • Whiteboards
  • Bakers supply run.

Wednesday, August 31 (6:10 PM)

  • Welcome Bruce Baker!
  • Power Cube Inventory
  • Shopping list


Monday, August 29 (3:20 PM)

  • Funding delays
  • Strategies with priorities (Prototyping, Documentation, Enterprise Training)
  • Brianna's todo list (see Brianna Log
    • Retorching undersized feet holder
    • Hopper Plates
    • Welder shakedown.
    • Install Drawers
  • Chris going on a supply run (Nuts, Fans, Muffler Pipe)

Wednesday, August 24 (began at 7:15 PM)

  • Discussion about progress on personal wiki logs and also progress made by Chris and Tom. Problems with using Media Wiki.
  • Shonda added picture to wiki log - and gained praise.
  • Discussed progress made on Power Cube documentation and problems encountered with wiki and graphics.
  • New and improved labor standards mandate 1 to 3 hours of "real work" in the OSE community.
  • Discussion about cleaning up the grounds, recycling the tin cans, glass, burning trash, etc.
  • Certified welders will arrive soon to help the effort.

Tuesday, August 23 (began at 5:20 PM)

  • Discussed importance of wiki logs for each participant
  • Spent time reviewing others' wikis, updating and giving suggestions for enhancements
  • Discussed trip to Sweigert Shop and progress made there
  • Discussed "to do" items for everyone:
    • Tom to get with Chris for graphics for the documentation
    • Chris to research milling machines, including new makes
    • Brianna and Marcin to move equipment to new workshop building

Monday, August 22 (began at 4:10 PM)

  • Discussed everyone's access to the wiki Logs - some were still lacking and followed up on getting everyone's log updated.
  • Discussed documentation efforts for Power Cube and CEB press. Tom said the biggest delays were in graphics and distractions.
  • Discussed to do tasks:
    • Tom - test electronics
    • Shonda - investigate milling machines for purchase
    • Briana - finalize CEB press
    • Everyone - Help with new structure, adding extenders to roof

Sunday, August 21 (began about 5:00 PM)

  • The first part of meeting addressed wiki and that everyone needs to be maintaining log entries for their participation.
  • The discussion then went into the tasks to be performed.
  • Then discussed immediate to do list - the first task was to work on the roof for the new shop space.