Tom is currently building Power Cube VII - optimizing form factor for ergonomics. The power cube after that is Power Cube VIII. See Machine Naming Convention.
Date
- Slated for Sat Nov 9 - Sun Nov 10.
- Tom Griffing is Guest Collaborative Production Run Director
Preparation
- Lathe up and running for spline coupler
- Tom has a coupler jig
- Lathe gearing via PowerCube + 6 Spline PTO Motor
BOM
- How much of http://opensourceecology.org/wiki/Power_Cube_6/Bill_of_Materials is still accurate?
Fabrication Diagram
Fabrication
Coupler -