Seed Home Workshop Preparation Process
Jump to navigation
Jump to search
OBI will be offering Seed Home and Aquaponic Greenhouse builds in other locations starting in 2017. The general process for builds involves:
- Potential Client Suitability Assessment. Includes identifying closest materials supplier.
- OBI Client Contract - 4 months prior to build date. 2 Contracts - one is Site and Materials Prep, and other one is the OBI Build Contract.
- Site clearing up to gravel laying and foundation pour by Client - 3 months before build date. Client should expect 1 day clearing with Bobcat, 1.5 day to put up forms, and 1/2 day to pour and remove forms. OBI inspects this by 3 months within build date. Verification via pictures, etc.
- Inventory received, verified by Client, specifics verified by OBI including any part substitutions - 4 hrs.
- Event posting - 2 months before build date
The general steps involved in preparing for a workshop are, once all assets are developed:
- Client communications, initial contact - 5 minutes to send out Client Suitability Assessment Form.
- Client Communications - Client Suitability Assessment Form evaluation - 1 hr
- Initial Build Discussion - Client Expectations Assessment Form filled out during conversation - 1 hr
- Preliminary Contract signing - 2 hrs
- Materials ordering - client is responsible for receiving, and doing inventory. OBI verifies inventory - including consumables and tools. OBI verifies supplies and work environment - such as sawhorses. - 8 hrs
- OBI Client Checklist - once every item on checklist is affirmed, OBI Build Contract is signed.
- OBI Build Contract signed - 4 hrs
- Workshop publicity - generate list of interested groups. Once generated, that is a company asset of OBI. Then it takes 8 hours to execute - sending out announcement to all groups, etc. 8 hrs.
- Catering - 4 hrs to make calls and organize menu. Develop a standard menu that we adhere to.