May Production Plan

From Open Source Ecology
Jump to navigation Jump to search

Strategy:

  • List steps in order of duty – Power Cube to Tractor to CEB press
  • Assess capacity required
  • Allocate tasks to 6 fabricators and local shop
  • List risks and recovery plans
  • Assess daily, before and after workday
  • Draw up personnel plan, detailed

Week Goal:

  • Day 1: Power Cube Tested, 1 tank welded, 1 set of arms mounted, PC 2 Completed
    • Buy 2 starter switches
    • Buy 3 more 5-gallon tanks of hydraulic fluid
    • Buy remaining cylinders, hydraulic pumps and fittings, and power beyond fittings
    • Check on bandsaw blades -LMH
    • Test lathe for drilling, facing off, and fitting 2 fittings together
    • Torch out wheel mount plates
    • Torch wheel gussets - Thad
    • Weld wheel gussets to collars - Thad after Marcin
    • Get 4-set of wheels ready
    • Cut wheel chain to length
    • Figure out shaft design detail for couplers
    • Mount 1 set of loader arms
  • Day 2:
    • Assumptions - motor mount plates need to be marked.
    • Risk Recovery Plan - have Chris specify and draw the mounting plates - as a priority.
    • Have somebody else do the gas filler holes

Power Cube Tasks

See Power Cube Documentation

Mount Power Cube


Test Power Cube on Tractor


Order Outstanding Components

  • Order Power Beyond Fittings (5 sets) - [1]
  • Order 2 more CEB main cylinders
  • Order 4 more 1 cu in pumps
  • 1 cu in pump fittings
  • Order 4 more hose barbs

Build Hydraulic tanks

  • Work on 3 at a time
  • Grind tanks down to clean, including fuel tanks
  • Clean edges and bungs
  • Ream any necessary holes
  • Lay out 3 sets on welding table
  • Close off bungs with fittings
  • Tack everything
  • Weld
  • Assemble tank

Prepare Hydraulic system components

  • Mount suction strainer in tank
  • Mount suction strainer fittings up to 3/4" hose barb
  • Cut hose to size
  • Mount breather cap
  • Assemble return line filter assembly

Prepare Fuel Tank

  • Torch filler cap
  • Drill screw holes for filler cap
  • Determine fuel line orientation - with Chris
  • Torch hole for fuel line
  • Weld fuel hole bung
  • Weld bottom and top onto fuel tank

Prepare Engine and Pump Mounting

  • Trim engine shaft
  • Assess fittings for hydraulic pump
  • Put fittings on hydraulic pump
  • Cut plate for Engine Mount
  • Cut plate for hydraulic pump
  • [1] Cut angle for Power Cube Mount

Prepare Electrical System Components

  • [4] Cut lugs
  • [4] Drill lugs
  • Prepare battery to solenoid cable
  • Prepare solenoid to starter cable
  • Select solenoid location, drill frame, and attach solenoid to frame
  • Prepare charging wire, attach charging wire extension to engine
  • Purchase starter switches from Maysville
  • Search for wire at FeF
  • Wire up starter switches - kill wire, solenoid wire, power wire
  • Select location for starter switch
  • Install starter switch
  • Prepare and weld on mount for throttle cable
  • Attach throttle cable
  • Build battery box
  • Secure battery to battery box
  • Bolt on terminals

Weld Mufflers – do 8 more

  • Secure 8 close nips, 1”
  • Secure 8 elbows, 1”
  • Cut 2 rings – flange and end piece of large tube
  • Grind and ream rings
  • Prepare 1 washer – 1/2” - for closing inner tube
  • Prepare 1 closure of washer
  • Mark pattern for muffler flange
  • Torch muffler flange, use #1 torch head
  • Procure gasket material for mufflers

Tractor Tasks

See Tractor Documentation

See May Production Run Tractor Tasks

May Production Run New Generator Tasks

May Production Run Generator Tasks

May Production Run CEB Tasks

May Production Run CEB Tasks