To be taken up by Ian Midgley

  1. Fabrication o of sensor units for CEB press from raw components to encapsulated sensor
  2. Fabrication steps for soil loading drawer
  3. Edit of assembly procedure for entire frame, starting from components
  4. Building hopper shaker assembly
  5. Building of hopper superstructure and connection to frame
  6. Asembly and function of cylinder ajusters: forward, side to side, and drawer adjusters
  7. Documentation of CEB machine dimensions, piece by piece
  8. Hydrauilics hookup and operation procedure
  9. Brick pressing sequence explanation
  10. Sawmill: operation procedures from existing footage
  11. Tractor: wheel attachment procedure
  12. Tractor: loader mounting procedure
  13. Power Cube: overall assembly procedure starting from raw parts
  14. Soil pulverizer: overall assembly procedure
  15. Power Cube: wiring walkthrough
  16. CEB press: field operating procedure from setup to bricks pressed


To be Taken up by William Neal

The following steps were finished during my DPV an would therefore be best for me to finish.

  1. Assembly of the electronics box for the CEB
  2. Soil loading Drawer Fabrication instructions
  3. Frame assembly instructions
  4. Preparation of the Main Xylinder