Jeremy's Goals

From Open Source Ecology
Revision as of 20:11, 25 January 2009 by Jeremy (talk | contribs)
Jump to navigation Jump to search

Jeremy Mason

  • 12.02.08 Goals 1 month - I commit to researching, designing, drafting a bill of materials, project budget, and plan of implementation for the open source sawmill. I commit to publishing my research on the wiki for collaboration. I am picking up where Bob left off and when he returns we will work on the project together.

Review - Some design and research done in Dec, most done in Jan. Work on the workshop took a lot of time. Did some work on bill of materials, budget, etc in Jan. Put up some stuff on the wiki. Worked on 2d and 3d model of design.


  • Jan-Feb Goals - Finish design with 3d, get feedback on forestry forums, finish implementation plan, finish bill of materials, finish budget, put together marketing materials, blog post and market.

Timeline:

Jan 25-31:

  • Jan 25-27 - Work on design, finish design, test working movements of design, post design for review on sawmilling forums, make bill of materials, make implementation plan, order bearings and bolts
  • Jan 28 - Get materials, put together marketing materials
  • Jan 29-31 - Put together prototype space frame and platform, put together marketing materials, do more marketing

Feb 1-7 - Putting together prototype and marketing materials, marketing, blog posts on progress, raise more money for further progress.