General Checkpoints For Setting Up the Machine

  • Check the polarity of the power cables to the machine.
  • Set the machine up on level ground. Adjust the feet so all 4 feet touch the ground.
  • Check that no bolts are visibly loose
  • Never run the machine without the safety rope - which is also the safety disconnect for power to the machine

Checkpoints for Every Day of Operation

  • Check for spilled hydraulic fluid