FeF Prototyping Schedule 2013
Jump to navigation
Jump to search
Q2
- Product Lead, Documenter, Tech Community Manager, Ops Manager, recruited by April 1 - on board by June 17, 2013. June 17 - first meeting with Marcin, Katie, Audrey, Gary, and Rob on board full time. As people are getting on-boarded, the 6 in 60 Campaign is ongoing. See 6 in 60 Milestones for assessment of achievable goals.
The 3 month campaign for 2013 for Q3
Following 6 in 60 of Q2 - our goal is to master the rest of the mechanical infrastructures, which are based on steel and hydraulics - as relevant to agricultural and construction infrastructures. The tools covered in 6 in 60 are: first prototypes of Truck, Car, Backhoe, Bulldozer, and further prototypes of Ironworker and Microtrac.
From then, we will refine the CNC Torch Table and Hydrafabber, complete the punch element on the Ironworker.