Marcin,
We were doing 13X10 in a couple of hours with 3 people.
I think you could easily get the full floor done in a day. I would say you could average 100-150 bricks/person/day. In 2 hours, you should be able to lay the bricks (maybe even a bit less). If you had 3-4 hours for the sand, then you'd have plenty of time.
If you have 2 entrances, you can do it as an assembly line, too: You could get one team bringing sand (4), another team following leveling (2), another team compacting(2), another bringing bricks(2), and the final one laying the bricks (2).
You'd want to trade people out on the assembly so your haulers don't get too tired.
Good luck, Abe