The Liberator Full Release - Mechanical Fabrication

From Open Source Ecology
Jump to navigation Jump to search

Frame

The frame consists of 7/16" thick, 6" wide u-channel. The frame is the same as that found in Prototype 1. You can use that as a fabrication guide. See the pictures 1-3 of CEB_Prototype_1_Fab.

The Liberator Beta v2.0 is fabricated as follows. First, see the technical drawing for the overview:

Frame overview, see frame_overview.dxf (94.2 KB) from 01/20/2010 03:36 pm at Open+Pario

The u-channels are shown around the cylinder and below the hopper.

Here are some fabrication pictures:


Frame

The frame is design-for-disassembly. 1/2" bolts, grade 8, are used to hold the frame together. The main cylinder attaches to the bottom of the frame, and the opposing members are at the top of the frame. These sets of frame members withstand the entire pressure of the cylinder, 20 tons, with the use of 8 bolts. Thus, each bolt needs to withstand about 5,000 lb of shear force. The area of a 1/2" bolt (.2 sq in) at over 100ksi strength, indicates 20,000 lb shear force per bolt, or a safety factor of 4. The middle set of structural u-channel members do not undergo shear force, but only expansion force of the soil as it is pressed in the compression chamber.

The structural members of the frame are 8 in number. The verticals (2), bottom cylinder support (2), opposing support (2), and compression chamber (2). There are 2 non-structural u-channels (8" wide), which close the bottom part of the compression chamber, with little force acting against them. These are 1/4" thick, while all the other structural members are 7/16" thick.

Fig 1 shows the frame members, being aligned for Transfer Punching holes for the 1/2" bolts. The dimensions of the u-channel members are shown in the technical drawing referred to above - see frame_overview.dxf (94.2 KB) from 01/20/2010 03:36 pm at Open+Pario.

Fig 1. Frame members for alignment.

Clamp all the structural members together, while fitting the soil drawer (shown further down) to assure correct spacing. Transfer punch all the holes with machine positioned vertically so that all holes are accessible. See Fig. 2.

Fig. 2. Transfer punching holes.

Holes in the eight, short, u-channel members have already been punched with a 120 Ton Hole Puncher or similar, with capacity to punch 9/16" holes. The holes are 9/16" - as 1/2" punched holes would be slightly undersized.

The two, vertical u-channels are then drilled at the location of the transfer punch marks.

After drilling, the frame is bolted together, Fig. 3. After bolting the frame can stand vertically, ready for attachment of the arms, Fig. 4.

Fig. 3. Frame bolted together.
Fig. 4. Frame standing.

Cylinder

The main cylinder is a 5"x8"x2.5" (bore-stroke-rod) cylinder.The main cylinder has a press foot fabricated from 2 plates, each 1" thick, welded on top of the cylinder rod to make the press foot. The press foot consists of one 6"x12" plate, with the second plate being 4"x10". These 2 plates are welded together. Before these plates are welded together, the smaller plate is torched out to accommodate a 1.5", fine-threaded nut, and the nut is welded into this plate. The press foot is then screwed on to the rod, where the cylinder used has a rod with 1.5" fine threads and a shoulder. The shaft of the cylinder used is 2". In future versions, we need to source a cylinder with a 2.5" rod, as the 2" rod will bend in the present configuration in the condition of uneven soil loading into the compression chamber. For this reason, the press foot was modified in Maureen's machine - by welding 6" guides under the press foot to prevent the press foot from bending with uneven loads.

It appears that the best strategy for attaching the press foot would be to weld a 1/2" wall DOM shoulder around the cylinder rod, by welding on the inside of this shoulder at the top of the cylinder rod, and then welding this DOM to the press foot, and using gussets towards the long way of the press foot.

Cylinder Attachment

Once the main frame is bolted together, the cylinder is fitted, Fig. 5.

Fig. 5. Cylinder fitting.

The cylinder is extended to its fully-extended position (by using air pressure or hydraulic flow), and the location of the bottom clevis mounting position is selected accordingly. The position of the clevis mount may be selected such that the press foot tops out at 1/16" or 1/8" above the table surface, to accommodate slight deformation of the frame over time. The table surface is defined as the bottom surface of the soil-loading drawer. The 1/16" or 1/8" is compensated by the location of the position sensors.

The bottom of the cylinder is attached to the bottom, horizontal u-channels via a 1" cylinder pin. 1/2" wall, drawn-over-mandrel (DOM) tubing is welded to the bottom u-channels, and it butts up right to the cylinder clevis. The pin is 8" long, and the DOM is 2.5" and 3" long, with the longer DOM drilled to accommodate a 1/8" pin for holding the cylinder pin in place. The 1" pin is drilled also to accommodate the small pin.

The hole for the cylinder pin DOM is torched with an acetylene torch, and the DOM is welded in place as needed.

Sensor Assembly

Arms

Legs

Table

Drawer

Structure

Sensor

Drawer Guides

Secondary Cylinder Attachment

Hopper

Grate

Hopper Shaker

Structure

Sensor