Seed Home Workshop Preparation Process

From Open Source Ecology
Revision as of 02:28, 5 May 2016 by Marcin (talk | contribs) (Created page with "OBI will be offering Seed Home and Aquaponic Greenhouse builds in other locations starting in 2017. The general process for builds involves: #Potential Client Suitability Ass...")
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

OBI will be offering Seed Home and Aquaponic Greenhouse builds in other locations starting in 2017. The general process for builds involves:

  1. Potential Client Suitability Assessment. Includes identifying closest materials supplier.
  2. Contract signing - 4 months prior to build date. OBI inspects the foundation.
  3. Site clearing up to gravel laying and foundation pour by Client - 3 months before build date. Client should expect 1 day clearing with Bobcat, 1.5 day to put up forms, and 1/2 day to pour and remove forms. OBI inspects this by 3 months within build date. Verification via pictures, etc.
  4. Inventory received, verified by Client, specifics verified by OBI including any part substitutions - 4 hrs.
  5. Event posting - 2 months before build date

The general steps involved in preparing for a workshop are, once all assets are developed:

  1. Client communications, initial contact - 5 minutes to send out Client Suitability Assessment Form.
  2. Client Communications - Client Suitability Assessment Form evaluation - 1 hr
  3. Initial Build Discussion - Client Expectations Assessment Form filled out during conversation - 1 hr
  4. Contract signing - 2 hrs
  5. Materials ordering - client is responsible for receiving, and doing inventory. OBI verifies inventory.