Seed Home Workshop Preparation Process
Jump to navigation
Jump to search
OBI will be offering Seed Home and Aquaponic Greenhouse builds in other locations starting in 2017. The general process for builds involves:
- Potential Client Suitability Assessment. Includes identifying closest materials supplier.
- Contract signing - 4 months prior to build date. OBI inspects the foundation.
- Site clearing up to gravel laying and foundation pour by Client - 3 months before build date. Client should expect 1 day clearing with Bobcat, 1.5 day to put up forms, and 1/2 day to pour and remove forms. OBI inspects this by 3 months within build date. Verification via pictures, etc.
- Inventory received, verified by Client, specifics verified by OBI including any part substitutions - 4 hrs.
- Event posting - 2 months before build date
The general steps involved in preparing for a workshop are, once all assets are developed:
- Client communications, initial contact - 5 minutes to send out Client Suitability Assessment Form.
- Client Communications - Client Suitability Assessment Form evaluation - 1 hr
- Initial Build Discussion - Client Expectations Assessment Form filled out during conversation - 1 hr
- Contract signing - 2 hrs
- Materials ordering - client is responsible for receiving, and doing inventory. OBI verifies inventory.