  • Staking of forms - 1 hr for 'supercorners', 2 hours for all rest including string. Superstructure concept works.
  • 2 days of forms = 1 day 6 hours 6 people, day 2 from 8 to 1 PM = 66 hours + staking + grading
  • Grading - 2 people 6+8 hours = 14 hrs pre-grade
  • Smooth for 4 hours - bulk smoothing amd evening
  • Finish smooth for 4 hours - getting to a couple inches
  • Final smooth 2 hours - finishing off to 2 inches level

Totals

  • Grade - 24 hr
  • String - 3 hrs
  • Foundation forms - 66 hours
  • Pour - 4 hrs clusterf*** with 6 people. Initial troublespot was truck getting in right after a sliver of snow made traction difficult so even the 7% small grade did not allow traction. Spread gravel, had to use conveyor to transfer from one truck to another for a stuck truck. Boss came out to help. Mudsill anchors not taped. Forms blew out several inches on one end. Get data for next time.