Build Phase Time Breakdown for SH6+
Jump to navigation
Jump to search
| Phase | Target Hours (Low–High) | Notes / What’s inside |
|---|---|---|
| 1) Site & Foundation | 70–110 | Layout, excavation, foundation system, backfill/rough grade |
| 2) Structural Shell | 120–170 | Floor (if any), walls, roof, sheathing, WRB, dry-in |
| 3) Exterior Close | 60–90 | Windows/doors, roofing, siding/cladding |
| 4) MEP (All) | 100–150 | Plumbing + electrical + HVAC rough/trim (simplified routing assumed) |
| 5) Insulation & Air Sealing | 20–35 | Insulation install + air sealing details |
| 6) Interior Finishes | 110–170 | Wall finish, paint, flooring, cabinets/trim, fixtures/appliances |
| 7) Commissioning, Punch, Cleanup | 20–25 | Test/commission, punch list, final clean |
| Total | 500–750 | Low-end sums to 500; high-end sums to 750 |