As a general perspective - 12 projects need to be run in parallel, with a monthly prototyping cycle for 3 prototypes - to deliver the full GVCS by Dec. 21, 2011. There are 355 days left.

By January 15, we will release the complete Tractor Fabrication drawings and CEB Hybrid Microhouse plans.