Daily Product Development Meeting/Notes Oct 12-14
Jump to navigation
Jump to search
Fri, 18 Oct
Insert Microhouse plan for the day or link from another area in the wiki
Wed & Thurs, 16-17 Oct
No Production Meeting -- Marcin off-site; downtime for DPVs
Tues, 15 Oct
Agenda: 1) Backhoe fabrication plan: Outstanding design issues, work instructions, documentation, other, 2) Ironworker
- Ironworker - Audrey will create PDB for Ironworker modules in preparation for the sprint tonight
- Backhoe - Cylinders mounted; boom was not completed -- working it today; mount system for boom is done; mounting the boom to tractor with the quick attach plates; QA plates are ready for welding
- 3D design will need to be updated with new mounting plate position (flexible mounting of the control cylinders)
- Documentation - using notepad, voice record & pictures; utilizing Dozuki today as a real-time upload of documentation during fabrication
Mon, 14 Oct
Agenda: Backhoe fabrication plan: Outstanding design issues, work instructions, documentation, other
- Backhoe plan - Boom and cylinders today; stick tomorrow, testing on Wednesday. Work instructions are complete. Outstanding design issues: ref: stress analysis email from Jeffrey Stump.
Logistics issues: need 1" lock washers, 100 bolts -- Marcin now believes we can wait to pick up the bolts from MoKan and would like to delay getting lock washers as well because these are not necessary to test the backhoe. NOTE: We need to schedule a time to complete installation of the lock washers once testing is complete.