Marcin Daily
Promise: by 2 PM on Thursday.
Key Promises via management of my energy and attention towards managing commitments for 2 Weeks including specific timing for what by when and who owns the promise, so these are measurable and observable so someone (Scott) holds me accountable. Include navigation - making and managing promises - including mid-course correction. The 2 week plan is static, and navigation turns it dynamic. What conversations do I want to have? MAP - managing, action, practice
- What
- When
- Who owns
- Who accounts
3-5 Key Promises for Sep 13- Sep 27
Construction
- Water lines buried for infrastructure - by Tuesday
- Trenching done by Saturday - Yoonseo, Gabi, Graham
- Submersible pump purchase - by Wed. - by Parker - 240V, 1/4 hp or 1/3 hp, Menards, sub pump fittings pressure tank fittings, pressure switch, wiring (Romex) - DONE
- Deliver 2' tube - city Dept by Tuesday
- Bury well hole half way - Marcin by Wed
- Source pitless adapter - by Wed - - DONE
- Pressure tank set up in house - installation and parts - Marcin + Kent by Friday,
- Pitless adapter installed - adapter sourced by Fri Sep 21
- Access road completed from road to house
- Trees in the way trimmed - done
- culvert buried
- Gravel truck spreads gravel - order Gravel Parker
- How to bury fittings under ground - stainless fittings - - done
- Skirt around house - work day on Saturday - Sep 22
- Procedure documented - Marcin - 4 hrs - by Sep. 22
- Order insulation
- Order 6 mil poly
- Tractor work
- Gravel laying
Organizational Development
- Assessment of large funding opportunity from conxcorp.com - - DONE.
- Strategic Plan summarized and clarified - 4 hrs + send for review to Team
- Discussion with Craig - 4 hrs
- Branding - Marcin + Emily
- 4 conversation with emily - 4 coming weeks - output for 2 weeks is nailing down a promise and a character brief, and nail down positioning strategy - - done
- High level messaging with David - 2 weeks. Product: elevator pitch and core message of 4 pillars of OSE as in OSE Brand - - done until Character Stand
- Work Product - document ecology of OSE Brand Team
- Recruiting of Operations Manager - output is 3 conversations per day - Operations Manager Conversations with high level contacts - leads to 3 interviews at end of 2 weeks.
- Conversation on announcement - Stephanie, David, Karien, Craig, Sunny, Sonaar, Nate Mook, Donna, Gerard, Gerry Ohrstrom + network through these contacts, Aditya,
- Edit of Announcement - David
- Conversation on pay structure - Karien, Craig
- 2 hour working session per week with Gerard - Outcomes: identify a project management system improvement strategy, secure 2 hours of his time in active project management
- Brick press:
- Old CEB press operational - by Monday - Marshall + Yoonseo - or New CEB operational by Friday, Sep 28
- Foundation laid for microhouse prototype - Marcin owns the promise by Sep 27
- OSE Microhouse Prototype Design, Siting
- Leveling
- Gravel spread
- Forms - Microhouse Prototype Foundation
- Cement pour - cement calculations of 1.4 cu yd
- Fab procedure for microhouse documented - blueprints for experimental microhouse
- Full fab procedure for brick press
- Full ergonomics documentation of brick press
- Full video on build of press - Tristan