<html><iframe width="560" height="315" src="https://www.youtube.com/embed/ipwKt-aEucY?start=175" title="YouTube video player" frameborder="0" allow="accelerometer; autoplay; clipboard-write; encrypted-media; gyroscope; picture-in-picture" allowfullscreen></iframe></html> | <html><iframe width="560" height="315" src="https://www.youtube.com/embed/ipwKt-aEucY?start=175" title="YouTube video player" frameborder="0" allow="accelerometer; autoplay; clipboard-write; encrypted-media; gyroscope; picture-in-picture" allowfullscreen></iframe></html> | ||
*14 foot sections are laid down, so it's convenient for a scree board. Work in 14 foot strips: | |||
<html><iframe width="560" height="315" src="https://www.youtube.com/embed/B2vC66QQGDE?start=339" title="YouTube video player" frameborder="0" allow="accelerometer; autoplay; clipboard-write; encrypted-media; gyroscope; picture-in-picture" allowfullscreen></iframe></html> | |||
=Understanding Concrete Timing= | =Understanding Concrete Timing= |
Revision as of 21:01, 29 August 2021
Notes
- Get yourself a power trowel - [1]
- Polymesh F is an extra $5/yard for concrete work - [2]
- Fiber still requires rebar [3]
- Use Steel Fiber Concrete for strength - not available in many places.
Workshop Foundation
- 3000 sf build of prototyping area for the Seed Eco-Homes, for building a second workshop space, with various prototyping experiments from material production to large CNC machines, 2021. Large truss structure at Universal Prototyping Structure
Open Source Power Trowel
- Combo blade - that is what they have at Rentall
- This is their finish blade.
- In video below, they show float and trowel blades as separate?
Notes On Technique
- Source 1 - [4]
- Temporary screed posts explained here for larger slabs poured in sections:
- 14 foot sections are laid down, so it's convenient for a scree board. Work in 14 foot strips:
Understanding Concrete Timing
In good weather - power trowel is about 2 hours after pour is finished.
- 35 yard slab
- 2 guys screeing, 2 guys behind them moving concrete around - 4 person job
- Batched at 6.
- Arrived on site at 7.
- Finished pour 8:30
- Start mag floats on edges at 10:20 AM
- Edger at 10:30
- 2:15 hours after pour ready to walk on, sinks about 1/8"
- Float blades first, finish trowel blades second. Take off the float blades to use the finish blades.
- Power trowel started at 11 am at 2.5 hours after start of pour - with float blades first. Only 1+ hour for power trowel.
- Notes: effectively, go from screeing step - to edger - to power trowel. Edger can be avoided. Power trowel does both float and trowel.
Links
- Roman Concrete
- Solar Concrete
- Concrete Cutting Blade
- Polished Concrete
- Lime Concrete
- Micro Concrete Roofing (MCR)
- Concrete Polishing
- Concrete Mixer
- Concrete Fasteners
- Rosebud Concrete Pour
- Concrete
- Concrete Foundations
- Concrete in Cold Weather
- Concrete Slab
- Reinforced Concrete Pipe
- Advanced Concretes
- Concrete 3D Printers
- Concrete Paint