Line 28: | Line 28: | ||
#House wrap installation | #House wrap installation | ||
#Vinyl siding installation | #Vinyl siding installation | ||
#Trim installation | |||
#Deck EPDM installation | #Deck EPDM installation | ||
#Gutter installation, roof and deck | #Gutter installation, roof and deck | ||
Line 33: | Line 34: | ||
#Final landscaping with sod and tree plantings | #Final landscaping with sod and tree plantings | ||
#Rough interior framing | #Rough interior framing | ||
#Bath tub installation (includes water extension) | |||
#Stairway and landing installation | #Stairway and landing installation | ||
#Water supply manifold installation | |||
#Rough plumbing installation | #Rough plumbing installation | ||
#Utility channel around doors | |||
#Rough framing installation | #Rough framing installation | ||
#fiberglass insulation of roof and walls | #fiberglass insulation of roof and walls | ||
#Beadboard installation | #Beadboard installation | ||
# | #Spray painting of interior | ||
#PV system installation | #Electrical service box installation | ||
#Rough electrical wiring | |||
#Outlets, switches, shutoffs, 3 way light switch, and lights installation | |||
#Toilet installation | |||
#Sinks installation | |||
#Kitchen cabinet finishing and installation | |||
#Washer installation | |||
#Dishwasher installation | |||
#Water heater installation | |||
#Finish floor installation | |||
#Interior trim installation | |||
#Heat pump installation | |||
#PV system installation - structure and panels | |||
#PV system installation - balance of system components and wiring | |||
#Power Trailer maintanance and usage for onsite temporary power | #Power Trailer maintanance and usage for onsite temporary power | ||
This is divided into base rate of $25, and $1 for every additional certification. |
Latest revision as of 19:39, 24 July 2022
- Grading land using open source heavy machines or equivalent.
- Using and maintaining open source machines (tractor, backhoe, trencher, auger, cherrypicker, forks, power ladder, stump grinder, mulcher, mower) including the ability to use all the implements safely.
- Using and maintaining Power Cubes and replacing them on a machine for zero downtime.
- Site evaluation, site soil testing, site surveying, site aerial mapping, and site GIS. Surveying and GIS training at collaborating community college.
- Site grading with skid steering machine, and site excavation.
- Foundation marking and squaring.
- Foundation forms installation
- Foundation posthole augering
- Pre-foundation rough plumbing installation
- Concrete work including screeing, floating, troweling, and power trowelling.
- Installation of a frost protected footer.
- Sill plate installation
- Rough concrete polishing to 400 grit
- Exterior wall framing
- Exterior Door framing
- Exterior Window framing
- Exterior wall installation including doors and windows
- Top plate installation
- Floor joists installation
- Roof installation - main roof box
- Roof installation - rigig foam roof box
- EPDM installation on roof
- Door installation
- Interior door installation
- Door knob installation
- Deck framing and sheathing
- Deck installation
- House wrap installation
- Vinyl siding installation
- Trim installation
- Deck EPDM installation
- Gutter installation, roof and deck
- Foundation skirt installation including plants
- Final landscaping with sod and tree plantings
- Rough interior framing
- Bath tub installation (includes water extension)
- Stairway and landing installation
- Water supply manifold installation
- Rough plumbing installation
- Utility channel around doors
- Rough framing installation
- fiberglass insulation of roof and walls
- Beadboard installation
- Spray painting of interior
- Electrical service box installation
- Rough electrical wiring
- Outlets, switches, shutoffs, 3 way light switch, and lights installation
- Toilet installation
- Sinks installation
- Kitchen cabinet finishing and installation
- Washer installation
- Dishwasher installation
- Water heater installation
- Finish floor installation
- Interior trim installation
- Heat pump installation
- PV system installation - structure and panels
- PV system installation - balance of system components and wiring
- Power Trailer maintanance and usage for onsite temporary power
This is divided into base rate of $25, and $1 for every additional certification.