A-Z Instructionals: Difference between revisions

From Open Source Ecology
Jump to navigation Jump to search
Line 40: Line 40:
<ol><li value="17">[http://makeprojects.com/Project/CEB-Main-Frame-Assemble-U-Channel/1740/1 Assemble U Channel]-needs model
<ol><li value="17">[http://makeprojects.com/Project/CEB-Main-Frame-Assemble-U-Channel/1740/1 Assemble U Channel]-needs model
<li>[http://makeprojects.com/Project/Fitting-the-Main-Cylinder/1414/1 Fit the Main Cylinder]-needs model
<li>[http://makeprojects.com/Project/Fitting-the-Main-Cylinder/1414/1 Fit the Main Cylinder]-needs model
<li>[http://makeprojects.com/Project/CEB-Stretching-the-frame/1742/1 Stretch the frame]</ol>
<li>[http://makeprojects.com/Project/CEB-Stretching-the-frame/1742/1 Stretch the frame]
<li>[http://makeprojects.com/Project/CEB-Frame-install-smaller-components-and-weld-spacers/1744/1 Weld the spacers]</ol>





Revision as of 22:03, 16 December 2011

THIS PAGE IS FOR THE CEB PRESS


CEB instructionals to be transfered to Make Projects
CEB instructionals CAD Requests

Fabrication

Note: All make pages need a BOM for steps.

Structural Components

  1. Simple Plates
  2. Frame structural support components-Still needs fab drawings

Soil Loading System

Shaker

  1. Shaker Mount-Still needs fab drawings
  2. Shaker Hammer and Shaft-Still needs fab drawings, model
  3. Shaker Hydraulics

Hopper and Grate

  1. Hopper Supports and Grate Mounts
  2. Hopper Sheet Metal-Still needs fab drawings
  3. Hopper Mounting plate
  4. Grate-Still needs fab drawings

Machine Core

  1. Soil Loading Drawer-Still needs fab drawings
  2. Roller Guides-Still needs fab drawings, model

Main Frame

Main Frame Preparation
  1. Wide Cylinder Supports
  2. Main Frame Small Components
  3. Main Frame U-Channel Prep-Still needs fab drawings, model
Main Cylinder Preparation
  1. Make the Press Feet
  2. Prepare the main cylinder-needs model
Main Frame Assembly
  1. Assemble U Channel-needs model
  2. Fit the Main Cylinder-needs model
  3. Stretch the frame
  4. Weld the spacers



Still need to be added in MAKE:

Soil Loading System


Assembling the frame

You'll need to have finished all other components in Machine Core and Frame Preparation and 2 Leg Holders

Hydraulics

Shaker Assembly -Still needs fab drawings, assembling hydraulics needs to be above this, model

Assembly

Before beginning assembly, insure you have finished all of the components listed above in the fabrication step.

  1. Assemble the structural components
  2. Assemble the Soil Loading System
  3. Shaker Assembly -Still needs fab drawings, assembling hydraulics needs to be above this, model
  4. Adjust the Drawer
  5. Install the secondary cylinder
  6. Hard-line the main cylinder

Programming

An Arduino is the microprocessor that controls the CEB Press's actions. It must be programmed with the CEB Press's unique program for making bricks.

Source code can be found at github: https://github.com/OSE/ceb-controller

Old code: