#January 7 - disseminate [[OSE Enterprise Plan]] far and wide to seed the acquisition of the remaining $5M of $5.5M | |||
#January 31 - recuit [[Co-Founder]] or CEO |
Revision as of 01:49, 1 January 2012
Intro
As a general perspective - 12 projects need to be run in parallel, with a monthly prototyping cycle for 3 prototypes - to deliver the full GVCS by Dec. 21, 2011. There are 355 days left.
GVCS Milestones and Strategy
- January 7 - disseminate OSE Enterprise Plan far and wide to seed the acquisition of the remaining $5M of $5.5M
- January 31 - recuit Co-Founder or CEO