Cris Log: Difference between revisions
Jump to navigation
Jump to search
No edit summary |
No edit summary |
||
(15 intermediate revisions by one other user not shown) | |||
Line 1: | Line 1: | ||
==Thur. 7 Aug. 2014== | |||
*Started work on dozuki microhouse 3 wall modules [http://opensourceecology.dozuki.com/Guide/Module+3a%2Bb/158] | |||
==Thur. 5 Jun. 2014== | |||
*Uploaded [[File:CEBPressSolenoidAssembly.skp]] | |||
*Uploaded uncorrupted [[File:CEB Press 6 Fabrication Drawings.zip]] | |||
*Got dimensions of Solenoid Assembly Hydraulic connections for updating of CAD models [https://opensourceecology.trovebox.com/photos/album-15/token-40e2e0b983/list see photos of actual assembly] | |||
*Created schematic of Solenoid Assembly with Hydraulic Connectors in [https://docs.google.com/presentation/d/1SUUtXan2g-ZltK5WlgeAXnqHiHaWgqLzG8JlQRqrjkc/edit#slide=id.g1d984a886_017 google presentation] | |||
*Created [[Lasersaur_Exterior_Panel_Installation]] to document current status of Lasersaur exterior panel installation | |||
*Helped Organize workshop | |||
*Disassembled solenoid valve assembly and began cleaning/degreasing components in preparation for reassembly | |||
==Wed. 4 Jun. 2014== | |||
*Started documenting [https://docs.google.com/presentation/d/1SUUtXan2g-ZltK5WlgeAXnqHiHaWgqLzG8JlQRqrjkc/edit#slide=id.g1db0c2aca_4029 CEB 6 Solenoid Assembly Manual] | |||
*Uploaded [[File:SolenoidAssembly.FCStd]] | |||
*Removed Solenoid Assembly from old Brick Press for updating FreeCAD model & for cleaning/degunking | |||
*Reassembled CEB Press with a team [[https://opensourceecology.trovebox.com/p/4kq?sortBy=dateUploaded,desc CEB Press]] | |||
==Tues. 3 Jun 2014== | |||
*Documented problems encountered during [http://opensourceecology.org/wiki/Lasersaur_Exterior_Panel_Installation Lasersaur Exterior Panel Installation] | |||
*Started Workshop reorganize and fixed some power tool plugs and extension cord ends. | |||
*Worked with a team to reassemble the CEB Press. Learned it is important to have a CAD model that matches the actual model. Also good to replace nuts and washers onto corresponding bolts while disassembling in order to simplify reassembly. | |||
==Mon. 2 Jun 2014== | ==Mon. 2 Jun 2014== | ||
*Sketchup practice | *Sketchup practice | ||
*[[CEB Press 6 - Drawer Guides - Build Instructions]] | *[[CEB Press 6 - Drawer Guides - Build Instructions]] | ||
*Started Mounting Lasersaur CNC Laser Cover Plates: need to drill additional holes as per Lasersaur Manual | *Started Mounting Lasersaur CNC Laser Cover Plates: need to drill additional holes as per Lasersaur Manual | ||
*Edited Lasersaur CAD model to include dimensions and location of panel holes [ | *Edited Lasersaur CAD model to include dimensions and location of panel holes [http://opensourceecology.org/wiki/File:LasersaurTopPanels.jpg],[http://opensourceecology.org/wiki/File:LasersaurTopDoorPanels.jpg],[http://opensourceecology.org/wiki/File:LasersaurFrontDoorPanels.jpg],[http://opensourceecology.org/wiki/File:LasersaurRightSidePanel.jpg],[http://opensourceecology.org/wiki/File:LasersaurLeftSidePanel.jpg],[http://opensourceecology.org/wiki/File:LasersaurFrontPanels.jpg] | ||
==Sat. 31 May 2014== | ==Sat. 31 May 2014== | ||
*Finalized prep for OSE | *Finalized prep for OSE | ||
*Installed software recommended in DPV Offer Letter | *Installed software recommended in DPV Offer Letter | ||
[[Category:Logs]] |
Latest revision as of 01:24, 24 January 2016
Thur. 7 Aug. 2014
- Started work on dozuki microhouse 3 wall modules [1]
Thur. 5 Jun. 2014
- Uploaded File:CEBPressSolenoidAssembly.skp
- Uploaded uncorrupted File:CEB Press 6 Fabrication Drawings.zip
- Got dimensions of Solenoid Assembly Hydraulic connections for updating of CAD models see photos of actual assembly
- Created schematic of Solenoid Assembly with Hydraulic Connectors in google presentation
- Created Lasersaur_Exterior_Panel_Installation to document current status of Lasersaur exterior panel installation
- Helped Organize workshop
- Disassembled solenoid valve assembly and began cleaning/degreasing components in preparation for reassembly
Wed. 4 Jun. 2014
- Started documenting CEB 6 Solenoid Assembly Manual
- Uploaded File:SolenoidAssembly.FCStd
- Removed Solenoid Assembly from old Brick Press for updating FreeCAD model & for cleaning/degunking
- Reassembled CEB Press with a team [CEB Press]
Tues. 3 Jun 2014
- Documented problems encountered during Lasersaur Exterior Panel Installation
- Started Workshop reorganize and fixed some power tool plugs and extension cord ends.
- Worked with a team to reassemble the CEB Press. Learned it is important to have a CAD model that matches the actual model. Also good to replace nuts and washers onto corresponding bolts while disassembling in order to simplify reassembly.
Mon. 2 Jun 2014
- Sketchup practice
- CEB Press 6 - Drawer Guides - Build Instructions
- Started Mounting Lasersaur CNC Laser Cover Plates: need to drill additional holes as per Lasersaur Manual
- Edited Lasersaur CAD model to include dimensions and location of panel holes [2],[3],[4],[5],[6],[7]
Sat. 31 May 2014
- Finalized prep for OSE
- Installed software recommended in DPV Offer Letter