Marcin Daily: Difference between revisions
		
		
		
		
		
		Jump to navigation
		Jump to search
		
				
		
		
	
| (24 intermediate revisions by the same user not shown) | |||
| Line 2: | Line 2: | ||
Key Promises via management of my energy and attention towards managing commitments for 2 Weeks including specific timing for what by when and who owns the promise, so these are measurable and observable so someone (Scott) holds me accountable. Include navigation - making and managing promises - including mid-course correction. The 2 week plan is static, and navigation turns it dynamic. What conversations do I want to have? MAP - managing, action, practice  | Key Promises via management of my energy and attention towards managing commitments for 2 Weeks including specific timing for what by when and who owns the promise, so these are measurable and observable so someone (Scott) holds me accountable. Include navigation - making and managing promises - including mid-course correction. The 2 week plan is static, and navigation turns it dynamic. What conversations do I want to have? MAP - managing, action, practice  | ||
*What  | |||
*When  | |||
*Who owns  | |||
*Who accounts  | |||
=3-5 Key Promises for Sep 13- Sep 27=  | |||
=3-5 Key Promises=  | |||
==Construction==  | ==Construction==  | ||
*Water lines buried for infrastructure  | *Water lines buried for infrastructure - by Tuesday  | ||
**Trenching done - Yoonseo, Gabi, Graham  | **Trenching done by Saturday - Yoonseo, Gabi, Graham  | ||
**Submersible pump purchase  | **Submersible pump purchase - by Wed. - by Parker - 240V, 1/4 hp or 1/3 hp, Menards, sub pump fittings pressure tank fittings, pressure switch, wiring (Romex) - <span style="color:green">DONE  | ||
**Bury well hole  | **Deliver 2' tube - city Dept by Tuesday  | ||
**Pressure tank set up in house - installation and parts - Marcin + Kent  | **Bury well hole half way - Marcin by Wed   | ||
**Source pitless adapter - by Wed - - <span style="color:green">DONE  | |||
**Pitless adapter installed  | **Pressure tank set up in house - installation and parts - Marcin + Kent by Friday,   | ||
**Pitless adapter installed - adapter sourced by Fri Sep 21  | |||
*Access road completed from road to house  | *Access road completed from road to house  | ||
**Trees in the way trimmed  | **Trees in the way trimmed - <span style="color:green">done  | ||
**culvert buried  | **culvert buried  | ||
**Gravel truck spreads gravel  | **Gravel truck spreads gravel - order Gravel Parker  | ||
**How to bury fittings under ground - stainless fittings - - <span style="color:green">done  | |||
*Skirt around house - work day on Saturday - Sep 22  | |||
**Procedure documented - Marcin - 4 hrs - by Sep. 22   | |||
**Order insulation  | |||
**Order 6 mil poly   | |||
**Tractor work   | |||
**Gravel laying  | |||
==Organizational Development==  | ==Organizational Development==  | ||
*Assessment of large funding opportunity from conxcorp.com  | *Assessment of large funding opportunity from conxcorp.com - - <span style="color:green">DONE.  | ||
**Strategic Plan summarized and clarified - 4 hrs + send for review to Team  | **Strategic Plan summarized and clarified - 4 hrs + send for review to Team  | ||
**Discussion with Craig - 4 hrs  | **Discussion with Craig - 4 hrs  | ||
*Branding  | *Branding - Marcin + Emily  | ||
**4 conversation with emily - 4 coming weeks - output for 2 weeks is nailing down a promise and a character brief, and nail down positioning strategy    | **4 conversation with emily - 4 coming weeks - output for 2 weeks is nailing down a promise and a character brief, and nail down positioning strategy - - <span style="color:green">done  | ||
**High level messaging with David - 2 weeks. Product: elevator pitch and core message of 4 pillars of OSE as in [[OSE Brand]]  | **High level messaging with David - 2 weeks. Product: elevator pitch and core message of 4 pillars of OSE as in [[OSE Brand]] - - <span style="color:green">done until [[Character Stand]]  | ||
**Work Product - document ecology of [[OSE Brand Team]]  | **Work Product - document ecology of [[OSE Brand Team]]  | ||
*Recruiting of Operations Manager - output is 3 conversations per day with high level contacts  | *Recruiting of Operations Manager - output is 3 conversations per day - [[Operations Manager Conversations]] with high level contacts - leads to 3 interviews at end of 2 weeks.  | ||
**Conversation on announcement - Stephanie, David, Karien, Craig, Sunny, Sonaar, Nate Mook, Donna, Gerard, Gerry Ohrstrom + network through these contacts  | **Conversation on announcement - Stephanie, David, Karien, Craig, Sunny, Sonaar, Nate Mook, Donna, Gerard, Gerry Ohrstrom + network through these contacts, Aditya,   | ||
**Edit of Announcement - David  | **Edit of Announcement - David  | ||
**Conversation on pay structure - Karien, Craig  | **Conversation on pay structure - Karien, Craig  | ||
| Line 32: | Line 44: | ||
*Brick press:  | *Brick press:  | ||
**Old CEB press operational - by Monday - Marshall + Yoonseo  | **Old CEB press operational - by Monday - Marshall + Yoonseo - or New CEB operational by Friday, Sep 28  | ||
**Foundation laid for microhouse - Marcin   | **Foundation laid for microhouse prototype - Marcin owns the promise by Sep 27  | ||
***[[OSE Microhouse Prototype]] Design  | ***[[OSE Microhouse Prototype]] Design, Siting  | ||
***Leveling  | ***Leveling  | ||
***Gravel  | ***Gravel spread   | ||
***Forms - [[Microhouse Prototype Foundation]]  | ***Forms - [[Microhouse Prototype Foundation]]  | ||
***Cement pour  | ***Cement pour - cement calculations of 1.4 cu yd  | ||
**Fab procedure for microhouse documented -   | **Fab procedure for microhouse documented - blueprints for experimental microhouse  | ||
**Full fab procedure for brick press  | **Full fab procedure for brick press  | ||
**Full ergonomics documentation of brick press  | |||
**Full video on build of press - Tristan  | **Full video on build of press - Tristan  | ||
Latest revision as of 11:04, 24 September 2012
Promise: by 2 PM on Thursday.
Key Promises via management of my energy and attention towards managing commitments for 2 Weeks including specific timing for what by when and who owns the promise, so these are measurable and observable so someone (Scott) holds me accountable. Include navigation - making and managing promises - including mid-course correction. The 2 week plan is static, and navigation turns it dynamic. What conversations do I want to have? MAP - managing, action, practice
- What
 - When
 - Who owns
 - Who accounts
 
3-5 Key Promises for Sep 13- Sep 27
Construction
- Water lines buried for infrastructure - by Tuesday
- Trenching done by Saturday - Yoonseo, Gabi, Graham
 - Submersible pump purchase - by Wed. - by Parker - 240V, 1/4 hp or 1/3 hp, Menards, sub pump fittings pressure tank fittings, pressure switch, wiring (Romex) - DONE
 - Deliver 2' tube - city Dept by Tuesday
 - Bury well hole half way - Marcin by Wed
 - Source pitless adapter - by Wed - - DONE
 - Pressure tank set up in house - installation and parts - Marcin + Kent by Friday,
 - Pitless adapter installed - adapter sourced by Fri Sep 21
 
 - Access road completed from road to house
- Trees in the way trimmed - done
 - culvert buried
 - Gravel truck spreads gravel - order Gravel Parker
 - How to bury fittings under ground - stainless fittings - - done
 
 - Skirt around house - work day on Saturday - Sep 22
- Procedure documented - Marcin - 4 hrs - by Sep. 22
 - Order insulation
 - Order 6 mil poly
 - Tractor work
 - Gravel laying
 
 
Organizational Development
- Assessment of large funding opportunity from conxcorp.com - - DONE.
- Strategic Plan summarized and clarified - 4 hrs + send for review to Team
 - Discussion with Craig - 4 hrs
 
 - Branding - Marcin + Emily
- 4 conversation with emily - 4 coming weeks - output for 2 weeks is nailing down a promise and a character brief, and nail down positioning strategy - - done
 - High level messaging with David - 2 weeks. Product: elevator pitch and core message of 4 pillars of OSE as in OSE Brand - - done until Character Stand
 - Work Product - document ecology of OSE Brand Team
 
 - Recruiting of Operations Manager - output is 3 conversations per day - Operations Manager Conversations with high level contacts - leads to 3 interviews at end of 2 weeks.
- Conversation on announcement - Stephanie, David, Karien, Craig, Sunny, Sonaar, Nate Mook, Donna, Gerard, Gerry Ohrstrom + network through these contacts, Aditya,
 - Edit of Announcement - David
 - Conversation on pay structure - Karien, Craig
 - 2 hour working session per week with Gerard - Outcomes: identify a project management system improvement strategy, secure 2 hours of his time in active project management
 
 
- Brick press:
- Old CEB press operational - by Monday - Marshall + Yoonseo - or New CEB operational by Friday, Sep 28
 - Foundation laid for microhouse prototype - Marcin owns the promise by Sep 27
- OSE Microhouse Prototype Design, Siting
 - Leveling
 - Gravel spread
 - Forms - Microhouse Prototype Foundation
 - Cement pour - cement calculations of 1.4 cu yd
 
 - Fab procedure for microhouse documented - blueprints for experimental microhouse
 - Full fab procedure for brick press
 - Full ergonomics documentation of brick press
 - Full video on build of press - Tristan