Marcin Daily: Difference between revisions
Jump to navigation
Jump to search
Line 14: | Line 14: | ||
**Deliver 2' tube - city Dept by Fri | **Deliver 2' tube - city Dept by Fri | ||
**Bury well hole - Marcin by Fri | **Bury well hole - Marcin by Fri | ||
**Pressure tank set up in house - installation and parts - Marcin + Kent | **Pressure tank set up in house - installation and parts - Marcin + Kent by Friday, | ||
**Pitless adapter installed - adapter sourced by | **Pitless adapter installed - adapter sourced by Fri Sep 21 | ||
*Access road completed from road to house | *Access road completed from road to house | ||
**Trees in the way trimmed | **Trees in the way trimmed | ||
**culvert buried | **culvert buried | ||
**Gravel truck spreads gravel | **Gravel truck spreads gravel | ||
**How to bury fittings under ground - stainless fittings | |||
*Skirt around house | |||
==Organizational Development== | ==Organizational Development== |
Revision as of 21:34, 13 September 2012
Promise: by 2 PM on Thursday.
Key Promises via management of my energy and attention towards managing commitments for 2 Weeks including specific timing for what by when and who owns the promise, so these are measurable and observable so someone (Scott) holds me accountable. Include navigation - making and managing promises - including mid-course correction. The 2 week plan is static, and navigation turns it dynamic. What conversations do I want to have? MAP - managing, action, practice
- What
- When
- Who owns
- Who accounts
3-5 Key Promises
Construction
- Water lines buried for infrastructure
- Trenching done by Saturday - Yoonseo, Gabi, Graham
- Submersible pump purchase - by Saturday - by Parker - 240V, 1/4 hp or 1/3 hp, Menards, sub pump fittings pressure tank fittings, pressure switch, wiring (Romex)
- Deliver 2' tube - city Dept by Fri
- Bury well hole - Marcin by Fri
- Pressure tank set up in house - installation and parts - Marcin + Kent by Friday,
- Pitless adapter installed - adapter sourced by Fri Sep 21
- Access road completed from road to house
- Trees in the way trimmed
- culvert buried
- Gravel truck spreads gravel
- How to bury fittings under ground - stainless fittings
- Skirt around house
Organizational Development
- Assessment of large funding opportunity from conxcorp.com
- Strategic Plan summarized and clarified - 4 hrs + send for review to Team
- Discussion with Craig - 4 hrs
- Branding
- 4 conversation with emily - 4 coming weeks - output for 2 weeks is nailing down a promise and a character brief, and nail down positioning strategy
- High level messaging with David - 2 weeks. Product: elevator pitch and core message of 4 pillars of OSE as in OSE Brand
- Work Product - document ecology of OSE Brand Team
- Recruiting of Operations Manager - output is 3 conversations per day with high level contacts - leads to 3 interviews
- Conversation on announcement - Stephanie, David, Karien, Craig, Sunny, Sonaar, Nate Mook, Donna, Gerard, Gerry Ohrstrom + network through these contacts
- Edit of Announcement - David
- Conversation on pay structure - Karien, Craig
- 2 hour working session per week with Gerard - Outcomes: identify a project management system improvement strategy, secure 2 hours of his time in active project management
- Brick press:
- Old CEB press operational - by Monday - Marshall + Yoonseo
- Foundation laid for microhouse - Marcin and Kent own the promise
- OSE Microhouse Prototype Design
- Siting
- Leveling
- Gravel
- Forms - Microhouse Prototype Foundation
- Cement pour
- Fab procedure for microhouse documented - l blueprints for experimental microhouse
- Full fab procedure for brick press
- Full video on build of press - Tristan
- Full video on build of Microhouse - Tristan
Expansion Strategy
- Craig Campbell - securing $20M
- Gerard - deployed on project management
- David - deployed on messaging
- Emily - co-defining Hero's Story - brand implementation strategy
- Mr. Bonnell - after 4 weeks - brand implementation
- Hajj - after 4 weeks - brand implementation