=Window/Door Module=
=Window/Door Module=
==Development==
Initial ideas for window and door frames, as well as a gringo block for attaching frames and a block for service entrance of data and electricity.
[[File:Components Aug 15.jpg|900px]]
Here is a first pass at creating an instruction sheet for how to build a window frame module:
[[File:Window Frame.jpg|500px]]
This image shows the first idea of how the frames will set on the foundation. Marcin did not want to use gringo blocks for attachments as it seemed redundant to him, so the design was simplified. Rather than secure the frames to the foundation, the frames will be secured to to the CEB walls with numerous screws.
[[File:foundation with frames.jpg|500px]]
Next iteration of instruction sheets for door/window frame building. This is much more detailed, but sheets like this take a long time to create. This sheet was created before the use of the Dozuki platform was in full swing (or at least before I was aware that it was being used). -Chris
[[File:Measure_and_Mark_Door_p1.jpg|500px]]
[[File:Measure_and_Mark_Door_p2.jpg|500px]]


=Utility Module=
=Utility Module=

Revision as of 14:49, 19 March 2014

The MicroHouse is broken into modules to enable a social production model like all OSE machines/architecture.

Foundation Module

Development

This early drawing explored a stemwall idea for the MicroHouse foundation and looked at various ways of insulating the foundation and siding the building.

Foundation Detail 1.jpg

Marcin was very interested in continuing to experiment with the shallow insulated footer concept. Here is a drawing based on design discussions between Floyd and Marcin. More information about the shallow insulated footer concept can be found here.

edit

Based on conversations with Walter Grondzik, PE... One item we discussed was getting the best performance from the direct solar gain heating system (heating of the CEB floor by sun shining through windows). Walter highly recommended putting in a thermal break between the floor and the foundation. Without this break, there heat will travel easily from the floor to the foundation. He suggested a 1" thick piece of foam, but he agreed that a 1/2" piece would be acceptable. Even at 1", the plaster and a trim board would cover it.

Foundation section w thermal break.jpg

Here was the initial idea for foundation formwork, discarded in favor of the simpler, faster idea presented below in execution section.

Pipe and chase diagram.jpg

Execution

Precise dimensions for pipe layouts

Pipe layout dimensions.jpg

Notes:

  1. Measure and mark opposing interior form boards with dimensions listed.
       1a. Measure from outside of inner form board (in other words, from what will be inside of concrete).
  2. Put small nail into form top at location of mark - string between similar mark on opposing form board.
  3. Run designated pipes under foundation formwork and make sure vertical pipe is directly under 
     proper intersecting strings.
  4. 6" chase for future hydronics does not need to be at any slope.
  5. 2" graywater and 3" blackwater lines MUST BE AT 1/4" slope per 1' of length. 
     This is required for proper drainage, otherwise liquids will outrun solids.
  6. Pipe layout shows 6" chase running over 2" and 3" lines, however, it is typical to conserve as much 
     elevation as possible when exiting graywater pipes... best practice will be to run 2" and 3" pipe 
     out just below bottom of foundation formwork. 6" pipe will most likely run beneath level of 2" and 3" pipes.
  7. Run pipes past foundation forms by roughly 5' and cap with cardboard/duct tape or old rag, etc. 
     Leave vertical pipes at a length of 1' taller than foundation forms. Cap this end, as well. 
     Staking the vertical pipe in place with rebar will prevent it from getting disturbed.

Pipe Elevations:

edit


Instructions Sketches

Microhouse foundation p1.jpg

For allthread, do 2 at corners and 2 in middel - 4 per side. For blowout, do 2 of them per side - 1/3 way each. Rebar ends up at bottom 1/3 of boundation. Allthread about 5 inches down from top. Microhouse foundation p2.jpg

Stub out 8-12" of rebar.

Microhouse foundation p3.jpg

Do 4 pieces of allthred per side -

Microhouse foundation p4.jpg

Foundation BOM

Build Documentation

Assembling the MicroHouse foundation forms:


Pouring the concrete for the MicroHouse foundation:


Next, we installed the drain pipes, water inlet and the chase to enable thermal hydronics to connect to a future module.

Having proper fall on drainage pipes is essential. In order to facilitate measuring the fall on drain pipes at 1/4" per 1', a small 1" jig is taped to the end of a 4' level.

Jig on level.jpg


Strings were attached to the foundation form boards; intersections show where pipes come through floor. Final dimensions shown on marked up sheet to make any adjustments needed to utility module.

Strings on foundation.jpgPipe layout dimensions.jpgMarked up pipe layout sheet.jpg


3" blackwater pipe was installed first. Gravel was dug out, pipe was put in place and checked for proper fall. "Shit runs downhill," the old plumber's golden rule says, but it runs downhill best if it sloped at 1/4" per 1'. Too much fall, and liquids can outrun solids.

Blackwater w level.jpg


Always prime pipe before gluing to ensure a good bond. The vent pipe for the blackwater outlet (not shown in original drawing) penetrates the floor to come into the utility module. String intersections were used as guides and pieces were held in place to determine pipe lengths for cutting.

Priming pipe.jpgChecking pipe location.jpg


Once the 3" pipe was in place, a similar trench was dug out for the 2" line using the string as a guide. Here, the 2" and 3" lines are shown exiting the building. Both were kept low enough that the 6" line can go above them.

2 inch line excavation.jpg2 and 3 inch pipe exit.jpg


The last pipe to go in was the 6" chase that will eventually contain insulated PEX pipes to carry thermal energy to a future module. The 90 was too tall, so one of the bell-ends was cut off of it. Once the pipes were installed, the ends were capped with plastic bags and duct tape to avoid debris getting inside them before use.

6 inch pipe.jpg6 inch 90 cut.jpgCapping pipes.jpg



The end result... pipe stubs right where we want them to be!

Stubs.jpg

Window/Door Module

Development

Initial ideas for window and door frames, as well as a gringo block for attaching frames and a block for service entrance of data and electricity.

Components Aug 15.jpg


Here is a first pass at creating an instruction sheet for how to build a window frame module:

Window Frame.jpg


This image shows the first idea of how the frames will set on the foundation. Marcin did not want to use gringo blocks for attachments as it seemed redundant to him, so the design was simplified. Rather than secure the frames to the foundation, the frames will be secured to to the CEB walls with numerous screws.

Foundation with frames.jpg


Next iteration of instruction sheets for door/window frame building. This is much more detailed, but sheets like this take a long time to create. This sheet was created before the use of the Dozuki platform was in full swing (or at least before I was aware that it was being used). -Chris

Measure and Mark Door p1.jpg

Measure and Mark Door p2.jpg

Utility Module

Partition Wall Module

Loft Modules

Upper Wall Modules

Roof Modules