Revision as of 18:07, 17 February 2020
Commercial
- $1 for unstabilized, $1.20 for stabilized - [1]
Proejcted OSE Costs - Expected to be Attained at Summer X 2020
Hint: One scenario missing is soil digging, which adds 1.5 gallon per hour cost of fuel to the overall operation.
- Costs based on availability of on-site soil
- 6 block per minute machine - 8 hour shift - 1 gallon per hour for CEB, 0.5 gallon per hour for tractor (25% duty cycle assuming nearby pile of soil that has already been dug), one gallon per hour for soil mixer, local clay soil, 10% cement stabilized
- Total costs for 2880 block:
- 2.5 gal* 8=20 gal fuel = $50 at current gas prices
- Cement - $10 per bag for 100 block - 29 bags of cement - $290
- Labor - $25/hr for tractor operator, $15/hr for stacking block on pallets x2 - $440/day
- Water - 20 ml/block = 58 liters = 15 gallons at 2 cents - 30 cents in water
- Plastic wrap
- Pallets
Total costs -
Upload of Key Costs