Revision as of 00:19, 19 June 2011
Strategy:
- List steps in order of duty – Power Cube to Tractor to CEB press
- Assess capacity required and allocate tasks to 6 fabricators and local shop
- List risks and recovery plans
- Assess daily, before and after workday
- Draw up personnel plan, detailed
Power Cube Tasks
Prepare Electrical System Components
Weld Mufflers – do 8 more
- Secure 8 close nips, 1”
- Secure 8 elbows, 1”
- Cut 2 rings – flange and end piece of large tube
- Grind and ream rings
- Prepare 1 washer – 1/2” - for closing inner tube
- Prepare 1 closure of washer
- Mark pattern for muffler flange
- Torch muffler flange, use #1 torch head
- Procure gasket material for mufflers
Tractor Tasks
See May Production Run Tractor Tasks
May Production Run New Generator Tasks
May Production Run Generator Tasks