=5 Key Promises=
=5 Key Promises=
*Water lines buried for infrastructure, well set upon
**Trenching done - Yoonseo, Gabi, Graham
**Pressure tank set up in house - installation and parts
**Submersible pump activated - submersible pump purchased
**Pitless adapter installed
*Access road completed from road to house
**Trees trimmed
**culvert buried
**Gravel truck spreads gravel
*High level messaging with David - 2 weeks. Product: elevator pitch and core message of 4 pillars of OSE as in [[OSE Brand]]
*High level messaging with David - 2 weeks. Product: elevator pitch and core message of 4 pillars of OSE as in [[OSE Brand]]
**First step - document ecology of [[OSE Brand Team]] here
**First step - document ecology of [[OSE Brand Team]] here

Revision as of 20:00, 13 September 2012

Promise: by 2 PM on Thursday.

Key Promises via management of my energy and attention towards managing commitments for 2 Weeks including specific timing for what by when and who owns the promise, so these are measurable and observable so someone (Scott) holds me accountable. Include navigation - making and managing promises - including mid-course correction. The 2 week plan is static, and navigation turns it dynamic. What conversations do I want to have? MAP - managing, action, practice


5 Key Promises

  • Water lines buried for infrastructure, well set upon
    • Trenching done - Yoonseo, Gabi, Graham
    • Pressure tank set up in house - installation and parts
    • Submersible pump activated - submersible pump purchased
    • Pitless adapter installed
  • Access road completed from road to house
    • Trees trimmed
    • culvert buried
    • Gravel truck spreads gravel
  • High level messaging with David - 2 weeks. Product: elevator pitch and core message of 4 pillars of OSE as in OSE Brand
  • Assessment of $20M funding opportunity from conxcorp.com
  • 4 conversation with emily - 4 coming weeks
  • 5 conversations per day with high level contacts for recruiting of Operations Manager
    • Conversation on announcement - Stephanie, David, Karien
    • Conversation on pay structure - Karien
  • Brick press:
    • Old CEB press operational - by Monday - Marshall + Yoonseo
    • Foundation laid for microhouse - Marcin and Kent own the promise
    • Fab procedure for microhouse documented - l blueprints for experimental microhouse
    • Full fab procedure for brick press
    • Full video on build of press - Tristan
    • Full video on build of Microhouse - Tristan
  • 2 hour conversation per week with Gerard
    • Outcome: identify a project management system improvement strategy
    • Secure 2 hours of his time in active project management

Expansion Strategy

  • Craig Campbell - securing $20M
  • Gerard - deployed on project management
  • David - deployed on messaging
  • Emily - co-defining Hero's Story - brand implementation strategy
  • Mr. Bonnell - after 4 weeks - brand implementation
  • Hajj - after 4 weeks - brand implementation