== Modernized Steam Engine Project Plan == | |||
=== Notes from 13-14 Mar 2013 === | |||
Modernized Steam Engine Project Plan | Modernized Steam Engine Project Plan | ||
Notes from 13-14 Mar 2013: | Notes from 13-14 Mar 2013: | ||
Line 18: | Line 20: | ||
Note on Pure Energy Systems-- Mass.-based company, will research further. | Note on Pure Energy Systems-- Mass.-based company, will research further. | ||
== Notes from 15 Mar 2013 == | |||
- Researched boiler systems (watertube, monotube, firetube, etc) | |||
- COTS engines found to date do not meet specs (size/hp requirements) and seem to be costly | |||
- Notes about safety--need to ensure sufficient safety warnings and instructions are included in manuals/drawings/maintenance plans--significant risk for safety incident (to include notes wrt substitutions of lower performing boiler safety valves, etc) | |||
- Created QRL for supply/SMEs/resources | |||
- Began project plan--top level summary/intent/etc |
Revision as of 05:00, 16 March 2013
Modernized Steam Engine Project Plan
Notes from 13-14 Mar 2013
Modernized Steam Engine Project Plan Notes from 13-14 Mar 2013:
- Performed research on history of product from initial innovation to modern use
- Began technical analysis requirements: COTS availability analysis, independent innovation, & alternatives
- Reviewed product integration requirements--began drafting tech performance requirements/specs
- Noted comments in blogs wrt regulation requirements in some states in the US
- Collecting potential SMEs (orgs & individuals) list and contact information for possible recruitment
- Drafted outline for project plan:
- Product Description, Operational Concept, and Operational Requirements
- Product Cost Requirements
- Program Schedule
- Life Cycle Sustainment Requirements - maintainability, safety, human performance/human engineering, testability
- Manpower - System Development/Build Requirements, System Operator Requirements, System Maintenance Requirements
- Data Management - Product Interfaces (ICDs)
- Production Strategy
- Support Equipment - BOM, Supply
- Brainstorming, brainstorming, brainstorming
Note on Pure Energy Systems-- Mass.-based company, will research further.
Notes from 15 Mar 2013
- Researched boiler systems (watertube, monotube, firetube, etc) - COTS engines found to date do not meet specs (size/hp requirements) and seem to be costly - Notes about safety--need to ensure sufficient safety warnings and instructions are included in manuals/drawings/maintenance plans--significant risk for safety incident (to include notes wrt substitutions of lower performing boiler safety valves, etc) - Created QRL for supply/SMEs/resources - Began project plan--top level summary/intent/etc