- Grading land using open source heavy machines or equivalent.
- Using and maintaining open source machines (tractor, backhoe, trencher, auger, cherrypicker, forks, power ladder, stump grinder, mulcher, mower) including the ability to use all the implements safely.
- Using and maintaining Power Cubes and replacing them on a machine for zero downtime.
- Site evaluation, site soil testing, site surveying, site aerial mapping, and site GIS. Surveying and GIS training at collaborating community college.
- Site grading with skid steering machine, and site excavation.
- Foundation marking and squaring.
- Foundation forms installation
- Foundation posthole augering
- Pre-foundation rough plumbing installation
- Concrete work including screeing, floating, troweling, and power trowelling.
- Installation of a frost protected footer.
- Sill plate installation
- Rough concrete polishing to 400 grit
- Exterior wall framing
- Exterior Door framing
- Exterior Window framing
- Exterior wall installation including doors and windows
- Top plate installation
- Floor joists installation
- Roof installation - main roof box
- Roof installation - rigig foam roof box
- EPDM installation on roof
- Door installation
- Interior door installation
- Door knob installation
- Deck framing and sheathing
- Deck installation
- House wrap installation
- Vinyl siding installation
- Deck EPDM installation
- Gutter installation, roof and deck
- Foundation skirt installation including plants
- Final landscaping with sod and tree plantings
- Rough interior framing
- Stairway and landing installation
- Rough plumbing installation
- Rough framing installation
- fiberglass insulation of roof and walls
- Beadboard installation
- Bathroom
- PV system installation
- Power Trailer maintanance and usage for onsite temporary power