May Production Plan
Jump to navigation
Jump to search
Strategy:
- List steps in order of duty – Power Cube to Tractor to CEB press
- Assess capacity required
- Allocate tasks to 6 fabricators and local shop
- List risks and recovery plans
- Assess daily, before and after workday
- Draw up personnel plan, detailed
Week Goal:
- Day 1: Power Cube Tested, 1 tank welded, 1 set of arms mounted, PC 2 Completed
Buy 2 starter switchesBuy 3 more 5-gallon tanks of hydraulic fluid- Buy remaining cylinders, hydraulic pumps and fittings, and power beyond fittings
- Check on bandsaw blades -LMH
- Test lathe for drilling, facing off, and fitting 2 fittings together
- Torch out wheel mount plates
- Torch wheel gussets - Thad
Weld wheel gussets to collars - Thad after Marcin- Get 4-set of wheels ready
- Cut wheel chain to length
- Figure out shaft design detail for couplers
- Mount 1 set of loader arms
- Day 2:
- Assumptions - motor mount plates need to be marked.
- Risk Recovery Plan - have Chris specify and draw the mounting plates - as a priority.
- Have somebody else do the gas filler holes
Power Cube Tasks
- Trim engine shaft
- Assess fittings for hydraulic pump
- Put fittings on hydraulic pump
- Cut plate for Engine Mount
- Cut plate for hydraulic pump
- [1] Cut angle for Power Cube Mount
Prepare Electrical System Components
- [4] Cut lugs
- [4] Drill lugs
- Prepare battery to solenoid cable
- Prepare solenoid to starter cable
- Select solenoid location, drill frame, and attach solenoid to frame
- Prepare charging wire, attach charging wire extension to engine
- Purchase starter switches from Maysville
- Search for wire at FeF
- Wire up starter switches - kill wire, solenoid wire, power wire
- Select location for starter switch
- Install starter switch
- Prepare and weld on mount for throttle cable
- Attach throttle cable
- Build battery box
- Secure battery to battery box
- Bolt on terminals
Weld Mufflers – do 8 more
- Secure 8 close nips, 1”
- Secure 8 elbows, 1”
- Cut 2 rings – flange and end piece of large tube
- Grind and ream rings
- Prepare 1 washer – 1/2” - for closing inner tube
- Prepare 1 closure of washer
- Mark pattern for muffler flange
- Torch muffler flange, use #1 torch head
- Procure gasket material for mufflers
Tractor Tasks
See May Production Run Tractor Tasks
May Production Run New Generator Tasks
May Production Run Generator Tasks