- 1 Tue-Fri Feb 25-28, 2014
- 2 Mon Feb 24, 2014
- 3 Sun Feb 23, 2014
- 4 Sat Feb 22, 2014
- 5 Fri Feb 21, 2014
- 6 Thu Feb 20, 2014
- 7 Wed Feb 19, 2014
- 8 Tue Feb 18, 2014
- 9 Mon Feb 17, 2014
- 10 Sun Feb 16, 2014
- 11 Sat Feb 15, 2014
- 12 Fri Feb 14, 2014
- 13 Thu Feb 13, 2014
- 14 Wed Feb 12, 2014
- 15 Tue Feb 11, 2014
- 16 Mon Feb 10, 2014
- 17 Fri Feb 7, 2014
- 18 Thu Feb 6, 2014
- 19 Wed Feb 5, 2014
- 20 Tue Feb 4, 2014
- 21 Mon Feb 3, 2014
- 22 Sat Feb 1, 2014
Tue-Fri Feb 25-28, 2014
Moving!
Mon Feb 24, 2014
Finishing website - Community Page, Workshops, True Fans, Get Involved, Collaborators, Machine Dashboards. Speed issues need to be addressed, already increased WP php memory on server to 128M from 40.
Sun Feb 23, 2014
Beamed wireless (600 feet, omnidirectional antenna) to Microhouse. Varies from full signal to none - need to troubleshoot
Sat Feb 22, 2014
Installed water to Microhouse. Need to fix leak.
Fri Feb 21, 2014
Purdue University Lecture and Ball State University Lecture.
Thu Feb 20, 2014
Website 2014 timelines management - Website_2014#Timelines_Information
Wed Feb 19, 2014
U. W. Milwaukee and Marquette University lectures. Farm Plan 2014.
Tue Feb 18, 2014
7-9 morning Brick Press, reviewing Critical Path. Then travel - doing Community Page on new site. Lecture at Milwaukee School of Engineering.
Mon Feb 17, 2014
Beginning development of Brick Press Workshop in earnest. Attempting 6AM to 2 PM schedule with zero interruption at that time. Updated CEB Press Critical Path and Tasks. Pepared water connection to HabLab. Met with Fair Share Farm regarding FeF Farm Plan - 1200-1600 row feet of 12-15 summer and fall crops.
Sun Feb 16, 2014
Moved back to FeF. Adding interim water connection and refrigerator to Microhouse. Continuing website. Release plan for 1 week from now - 3 hours per day next week. Today RFP Template with Piston Engine Construction Set as an example - http://opensourceecology.dozuki.com/c/Module_-_Overall_Engine
Sat Feb 15, 2014
Working on 2014 Website.
Fri Feb 14, 2014
Writing content for 2014 Website - About, GVCS. Working on Status of Completion.
Thu Feb 13, 2014
Did Documentation for 2014 Website for new website.
Wed Feb 12, 2014
Development_Plan_2014-2015#Construction_Set_Approach
Tue Feb 11, 2014
Website 2014. 2 Year Plan. Frank Golbeck agrees to be on Review Board. Review process concept: Review Board works 1 hour on Month Plan Gantt/Critical Path Diagram with person on OSE team, and reviews at end of month - making sure to capture learnings of planned/actual start dates and planned/actual time in Gantt. Frank, Catherine, Bob Fishman, and Renee are good Board candidates, Frank approved already. Key: streamline process so 1 hr yields meaningful Critical Path and Spreadsheet - have these all set up prior to meeting, and meeting is a live edit.
Mon Feb 10, 2014
Kakwa Ecovillage Planning. Drawing up Speaker Contract.
Fri Feb 7, 2014
Visiting with Jeff Moe. 3D Printer Companies By Market Size. Peer Production Surveys.
Thu Feb 6, 2014
Started Collaboration Assessment and Planning Log. OSE 2 Year Plan.
Wed Feb 5, 2014
Finishing OSE 6 Month Plan. Started Website 2014.
Tue Feb 4, 2014
OSE 6 Month Plan. MJ Critical Path - adding spreadsheet. University Collaboration
Mon Feb 3, 2014
Working on Dev Plan, MJ Critical Path.
Sat Feb 1, 2014
Began 2 Year Plan - or Dev Plan. Decided to include Diaspora* for OSE social media. Working on complexity map spreadsheet - GVCS Machines and Modules.