=Production=
=Production Meeting Notes=
=Meeting Notes=
=='''October 28 - November 3'''==
==October 21-27==
===Mon, 21 Oct===
No notes taken!


===Tues, 22 Oct===
===Nov 18, 2013===
No notes taken!
*MH -- Need to install the stove today, Mark will work on siding
*Trencher -- issue with the plates vs the SketchUp mode, made corrections to the prototype, need to update CAD
*CNC TT -- Sam is up to speed on CNC TT status;


===Wed, 23 Oct===
===Oct 31, 2013===
'''Agenda:''' 1) Backhoe development status; 2) Microhouse; 3) Ironworker
'''Agenda:''' 1) Ironworker, 2) MH, 3) Infrastructure, 4) Logistics, 5) Documentation, 6) CNC Torch Table, 7) Construction
*Backhoe: One show-stopping problem: the tractor can't lift the backhoe -- t-shooting by focusing proper pressure in the power cubes
*Ironworker - Ironworker has legs; still needs a guide installed on the table--99% built; still need to update all of the documentation; upload pictures for legs and build documentation instructions; going to cut tubing today
**Goal today is to do some test digs
*MH -- Working on Dozuki after lunch; meeting with Dan Overby to discuss energy modeling;
*MH: Plumbed, electrical done; need to complete interior trim details; need to tile bathroom, flooring in the loft, and floor seal downstairs, touch up on outside stucco;  
*Infrastructure -- still raining, not going to have Jake come out today; Jake was able to remove the bricks around the stove so we can re-install when welding is complete
*Ironworker: Need to develop product concepts for outstanding modules
*Documentation --
*OTHER: Trencher is now a priority for November -- need to reflow Product Dev Schedule and update dev priorities ASAP
*CNC TT -- Hardware needs to be updated, but is working now; need to replace one of the motor mounts; wants to create some software for testing; is moving in 3 dimensions now
*Construction -- MH is the south: Ideal client -- Has land to build it, has the capital to build it (~$15K), has place for attendees to stay/camp, has experience with construction/planning/building, in the south, will dedicate a blog post to this, other logistics: would need to transport our equipment/tractor
*Other -- 1) Discussed Theodore/Haiti Project with Chris for his SA, 2) Marcin is focused on the Shuttleworth application, 3) Microcar -- Yann is willing to come out in Dec; received Shuttleworth grant; perhaps mid-Jan to Feb will be better -- need to coordinate
 
===Oct 30, 2013===
'''Held mini Production meeting today.'''
*Ironworker -- refined precision cutting, putting on feet today, continuing documentation
*MH -- Mark is getting more wood to complete trim
*Infrastructure -- Rick is going to come out today to finish digging the drain pipe; Sweiger has the stove, should be done Thurs/Fri
*Logistics -- Marcin & Dan depart on Fri. They will drive the truck to St Joe and Katie will take them to the airport in her car
 
===Oct 29, 2013===
'''Agenda:''' 1) Ironworker, 2) MH, 3) Infrastructure, 4) Logistics, 5) Documentation
*Ironworker -- Sheared 1x8 yesterday; captured documentation of the process -- shear documentation & useage; will be used as part of our workshop infrastructure; need to finish the table, level the table, complete the guide/backstop, and install feet--Dozuki guides will need more work as well; need to capture what was built in Sketchup
*MH -- need to complete documentation and upload to Dozuki, but this is a lower priority than the Shuttleworth documentation deliverables for the Ironworker and the Backhoe; Mark needs more wood to finish the framing; still has two more days of "finishing" work
*Infrastructure -- '''Stove:'''Sweiger is making the doors, Marcin wants to deliver the entire structure (frame, etc) so they can finish everything--then we will simply need to install it --- Marcin would like to build a second stove for the workshop for this winter; Marcin will call Sweiger so he can explain what work needs to happen with the frame and how to attach the doors; Marcin wants Mark to install the stove once its done; Marcin wants the bricks removed around the stove; '''Bush hog:''' Need to contact Gary to get status when he can come out (Katie)
*Documentation -- '''MH:''' He is uploading to Trovebox, reloading them to 900x600 resolution; Marcin would like for the MH to be divided into sub-folders (i.e. foundation, etc--use what is in Dozuki); Marcin wants to meet with Chris & Rob to work sort documentation (meet today at 1pm CDT); '''Backhoe:'''We are missing step instructions, etc for what Cory & Leandra did this summer during 6 in 60; need to ID what documentation is outstanding by each module; Marcin would like to focus Wed/Thurs focusing on documentation -- photos, work instructions, & utilize 3D graphics if we don't have photos for instructions
*Other: Dan is leaving tomorrow @3:35pm, needs a ride
 
===Oct 28, 2013===
'''Agenda:''' 1) Design Sprint, 2) Ironworker, 3) MH, 4) Infrastructure, 5) Logistics, 6) Documentation
*Design Sprint Update-- Created a full Dozuki guide for the Ironworker; needs some editing;
**Applying this model to the Laser Cutter project -- let's do this same model and get people to support the 3-4 day build process while@ Lasersaur; ACTION -- Marcin to develop a schedule & agenda for Lasersaur (Tues, Wed, Thurs); will advertise via the Blog & through the newsletter;
*Ironworker -- 2/3s re-assembled; switched tubing from 2/3 to 1/2; cutting 1x6s today;
*MH --
'''NOTE: meeting interrupted due to HabLab internet going down'''




Line 388: Line 412:
<!---------------------------------------------------------------------->
<!---------------------------------------------------------------------->
</html>
</html>
==Logs==
==Logs==
*[[Cody Log]]
*[[Cody Log]]
Line 431: Line 456:
[https://docs.google.com/a/opensourceecology.org/document/d/1ViixwxMwXGQpulr6DlymmxLcnc3r1yHr1uhZy-qBQkI/edit Microhouse Prototype Assessment]
[https://docs.google.com/a/opensourceecology.org/document/d/1ViixwxMwXGQpulr6DlymmxLcnc3r1yHr1uhZy-qBQkI/edit Microhouse Prototype Assessment]


==Mon, 14 Oct==
'''Agenda''': 1) Backhoe fabrication plan: Outstanding design issues, work instructions, documentation, other, 2) Ironworker
*Ironworker - Audrey will create PDB for Ironworker modules in preparation for the sprint tonight
*Backhoe - Cylinders mounted; boom was not completed -- working it today; mount system for boom is done; mounting the boom to tractor with the quick attach plates; QA plates are ready for welding
**3D design will need to be updated with new mounting plate position (flexible mounting of the control cylinders)
*Documentation - using notepad, voice record & pictures; utilizing Dozuki today as a real-time upload of documentation during fabrication
==Mon, 14 Oct==
'''Agenda''': Backhoe fabrication plan: Outstanding design issues, work instructions, documentation, other
*Backhoe plan - Boom and cylinders today; stick tomorrow, testing on Wednesday. Work instructions are complete. Outstanding design issues: ref: stress analysis email from Jeffrey Stump.
Logistics issues: need 1" lock washers, 100 bolts -- Marcin now believes we can wait to pick up the bolts from MoKan and would like to delay getting lock washers as well because these are not necessary to test the backhoe. '''NOTE: We need to schedule a time to complete installation of the lock washers once testing is complete.'''
==Fri, 11 Oct 2013==
'''Meeting Minutes'''
*'''Backhoe''' - Missing pivot, few details such as cylinder mounting are needed. A good strategy would be to build the items that we are for sure about, add legs. Marcin volunteered to draw the pivot cylinder mount in sketch up. Can start build of pivot parts - do a complete fab procedure (Dan has completed much of this on paper). Is there a way to tag team the fab procedure? Such as uploading pictures every 5-10 minutes for every step - and have the steps documented on paper or sketch up? Where is Rob on documenting the fab procedure? Rob needs (hurting ourselves with the phoenix message because there is no wording) some wording - description of how something is being put together. Dan will take notes on paper, capturing how the assembly is coming together.
**Discussion about how to capture the changes to the step instructions as we are assembling the product. Reviewed the work instructions that Rob produced.
**Outcome - Phoenix method needs to have steps written underneath each picture - the technical expert (the person who designed the product needs to write the step instructions) During the build, issues and confusing steps need to be updated for laymen understanding simply using pen and ink.
***Small issue - Dan's step instructions are handwritten - rather than transferring them to a typed version, we will move forward with the handwritten instructions - Dan will transfer it online later (time issue, Dan has to leave tomorrow).
***Big change - Discussed writing everything down - Dan is game to write everything down
**Cody - Feet, Dan - Bolts, Marcin - pivot mount
==Thurs, 10 Oct 2013==
'''Agenda:'''
#'''Backhoe Status: 1) Pivot  2) Stick - motion analysis, 3) Quick Attach - Concept Drawing '''
#'''Documentation Status'''
#'''Microhouse'''
#'''Ironworker: 1) Development board(s), 2) Problem Statement, 3) Outstanding tasks for remote collaborators'''
'''Backhoe Status'''
*Legs
*Pivot: James W. sent model that mounts the hydraulic cylinders -- need to review it, looks good upon cursory review and determine integration points
*Quick Attach mount -- mostly done; may need to punch holes; need to determine structural support around the quick attach
*Need to do a ROM for the boom and pivot
*ROM for the legs for 2ft of vertical motion; check fit for cylinders
*Need BOM, work instructions
'''Dcoumentation'''
*Emmett is exporting and working on LifeTrac 6 photo editing
*Rob is focused on Dozuki LifeTrac documentation for Shuttleworth
'''Microhouse'''
*Cody is working on the roof
'''ACTIONS'''
#Rob will work out a process to direct remote collaborators to real-time help with video and photo editing, instructions, etc for Dozuki...will try to gett his done for implementation on Monday
'''Sidebar Discussion'''
Agenda: 1) Backhoe build & manpower, 2) Ironworker problem statement, schedule, design needs, 3) Stress analysis direction for the Backhoe
#Get Mark for the build on Mon-Fri next week & Mon-Tues following week
#Ironworker Problem Statement 1) Need to a guide and/or reinforced pivot to allow the arm to move straight vertically with no lateral movement, 2) The pivot needs to be mounted closer to the body to increase stability, 3) The pivot plates need to be bound closer together, 4) Design a punch element, 5) Need a work table with clamping mechanisms and integration points, 6) Design feet for more stabilization(angle mounted to the side).
#Ironworker Schedule: Ironworker Sprint on 15 Oct from 6-7pm CDT to get RCs to begin design work, will begin buildout NET Oct 23
#Ironworker Design Needs: punch element, table & feet; plus an infographic
#Stress analysis for backhoe: 1) Need cylinder force for the teeth of the bucket; 2) How much does it weight?, 3) Need force on each of the cylinders for the boom, stick and bucket at the beginning and end of motion. First, will need a completed design (due COB today, most likely)
'''Wrap Up'''
Agenda: 1) Backhoe Design Status, 2) Documentation, 3) Other: Ironworker Sprint, Visa options
Backhoe - Legs are 70% done, when complete we can start work instructions for pivot & legs; quick attach needs to be complete, and need to complete the ROM for the boom & stick
Documentation - Emmett's animations look great; Rob is in the process of uploading to Dozuki; on Latakoo right
Ironworker - confirmed for 15 October, that gives 1 week to design, 1 to build / test
Visa Status - Cyril has concerns over coming on a tourist visa; researching requirements for a B1 visa under "Training"; a J1 visa is expensive and would takw time -- may not fit our mission as well as the B1; need to contact the Business Visa office tomorrow for more information
Documentation: Rob is flying in late Sun night and will either rent a car or stay in a motel near the airport; plans to stay 2-3 days for Backhoe documentation.
==Wed, 9 Oct 2013==
'''Agenda:'''
#'''Backhoe Status: 1) Pivot - Sketchup, 2) Stick - motion analysis, 3) Quick Attach - Concept Drawing '''
#'''Documentation Status'''
'''Backhoe''' - continue design & ROM analysis
'''Documentation''' - Emmett will continue deconstruction analysis & Rob is working on Prezi
'''Wrap Up'''
*Backhoe Status:
**Pivot: Sketchup design is 95% done; BOM is next, then assembly work instructions, need to do hydraulics -- hydraulics should be 16" pin-to-pin
**Quick attach:  INW & interface piece
**Found a design flaw -- there isn't enough space for the pivot cylinders; Dan is developing a work around
*Documentation:
**Emmett needs to re-do one animation for the deconstruction animation on the LifeTrac 6; its going to take a long time to export the clips though--Emmett is researching to see if there is a way to export a large batch vs individuals
**Emmett's next step: edit & import photos to Trovebox via jpeg; needs resolution standard (must be at least 400x400)
**Rob recorded the Prezi for The Feast
**LifeTrac 6 Documentation: ready for replication -- wheels & cab; can ID what works and what doesn't
*Logistics:
**Prototyping material for scaled modeling; Audrey is going to Hammerspace on Friday to cut more materials
**10" Bolts from MoKan - won't be here until Wed / Thurs next week; workaround: use threaded rods and cut to size
*Other: Cody had a fundraising idea for future Microhouse construction; Katie took notes and will develop
'''Tomorrow's Plan'''
*Microhouse: Handyman Donnie bailed on us, we are going to pursue Labormax and operate within their confines
==Tues, 8 Oct 2013==
'''Agenda:'''
#'''Backhoe Status: pivot'''
#'''Microhouse Update: One DPV plus a temp worker (trying to get Mark), will work on the MH roof on Thurs'''
#'''Documentation Status'''
#'''Logistics:''' 1) Cylinder order, 2) Other parts that may be 'long lead' orders? (i.e. 10" bolts?), 3) Add'l Rapid Prototyping materials
'''Backhoe Status'''
*Dan suggested using trunions cylinders may work; Marcin brought up issues with using these cylinders wrt sourcing: price & availability; may be able to modify existing cylinders through a weld which will negate adding a special part--may explore welding but there is a risk with welding as well.
**Way forward: Pursue solution that is a single control that gives us 160-170 degrees rotation; draw in LibreCAD--perform analysis, build a scaled model--perform analysis; draw in SketchUp; contact Design Sprinter that offered to do stress analysis
*Stick: need to do motion analysis
*Quick attach: develop a concept drawing for the Quick Attach, need to design the "female" part that is mounted to the backhoe
'''Microhouse'''
*Cody will lead roofing on Thurs
'''Documentation Status'''
*Emmett will try and do the deconstruction animation today; he has been grouping appropriate parts within the cab
*Rob will go through the video of the cab to break down into a script to assist Emmett's efforts; Rob is also working on a video of the MH
'''Logistics'''
*Cylinder order: not yet
*Long Lead parts: 10" bolts from MoKan x 100, 1" washers x 100
*Prototyping materials: screws, 80 pages of what we have; what is the size (working area) of their laser cutter?
*Additional prototyping materials: screws,
'''Actions'''
#Backhoe: Dan is working Trig analysis; Marcin is doing LibreCAD drawing; Cody is
#Modeling: Cody is grinding down screws for the 3D modeling
#Inventory: Cody is going to perform inventory
#Audrey will call labor max to reserve Mark or other for roofing
#Audrey will source laser cutting in KC - get info on system
'''Wrap Up'''
#Backhoe pivot status: Geomoetry C/W, starting Sketchup; Maercin is working paper models exploring other ideas, Dan completed 2D LibreCAD pivot drawing; Will need to reassess the part that attaches to the quick connect for integration issues
#Modeling:C/W, screws ground down
#Inventory: Cody inventoried all of the plates; we do not need to buy cylinders; will likely need more steel cut -- need to determine last due date for BOM
#Roofer: Donnie, a local handyman, is coming out on Thurs and will work with Cody.
#Laser Cutter source: Audrey is getting Hammerspace membership, calling for more details
#Documentation: Rob is still digitizing footage from MH, Roofing footage is done; Emmett is struggling -- difficult to control Sketchup animation--taking numerous attempts to gain a smooth motion.
==Mon, 7 Oct 2013==
'''Agenda: 1) Backhoe Status, 2) Ironworker Status, 3) Microhouse Status, 4) Documentation'''
'''Backhoe'''
*'''Goal''': Decide design vector for pivot by COB today via Tech Tree of Choices; begin 3D modeling of Design in Sketchup
*Backhoe Pivot:
**Using Laser cutter pieces to build a small scale pivot (blog input & newsletter topic)
**Dan & Cody created a viable option that will give us 160 degrees of motion (goal is 180 degress -- 90 degrees on each side)
**Industry standard includes additional control mechanisms on the side of the pivot to allow for additional ROM
**Need to complete a Tech Tree of Choices to determine path forward
**Need to use LibreCAD to do a quick 2D analysis of ROM
**Does 180 degree ROM apply to industry standard Backhoes that do not use a gearbox? What ROM do they get?
**Discussion on custom work: may integrate minor custom work into design to allow for greater ROM; need to include these as options for analysis of complexity
*We have 8" and 10" cylinders; but they may not have the correct diameter cylinders; may need between 8-12" -- let's order what we need today
*Backhoe Bucket:
**Need to determine proper pin mounting
'''Ironworkwer'''
*Tabled --Need to discuss with Marcin and roll into schedule
'''Microhouse'''
*Microhouse: Need to finish roof...work this into Ironworker / Backhoe schedule; get additional manpower to assist with this from temp agency
'''Documentation'''
*Trovebox - DPVs will need to use Rob's login to upload from smartphones
**Need to create a DPV General User account so staff accounts are not compromised
**Need to provide feedback to Trovebox for improvement; we are part of a beta-test...need to include youtube, vimeo, Dozuki access, LibreCAD for simple 2D design -- need instructionals
*New documentation method -- 1) Explode the diagram; 2) Play it in reverse to create a dis-assembly to assembly using animation (i.e. the Phoenix Method w/ animation). Issue: capturing the animation on screen; need to work this out (Rob will work this and get back to us). If it works, they will try the cab.
'''Other'''
*Emmett is likely leaving Saturday or Sunday
*Time off -- If DPVs need some downtime, speak up!
*Workshop cleanup
*Media focus this week: Rapid prototyping capability using laser cut pieces
*Meetings: 9am Daily Product Development Meeting; 4:30pm Wrap-up
'''Actions'''
#Work on animation and sequencing for documentation purposes and work out our methodology -- Rob & Emmett
#Tech tree of choices for pivot -- Cody
#Build pivot in LibreCAD for 2D ROM analysis -- Dan
#Order cylinders --  Marcin will order if needed
#Shop cleanup -- ALL prior to workshop work today
#Add info to DPV O&M Board: youtube, vimeo, LibreCAD, & Dozuki access -- Audrey (with Rob's help)
#Create a DPV General user account for Trovebox? -- Rob
#Integrate Tech Tree of Choices instructions / protocol into Dev Board -- Marcin
'''End of Day Wrap Up'''
Agenda: 1) Status on actions #1-3, 2) Decision: #4, 3) Other issues, 4) Next steps
'''Status of Actions'''
*Emmett needs the LFT 6 step instructions (Audrey to send from Gary's Log)
*We will need to take each frame and string them together; need to create procedures process is refined
*Used new capture program iShowU HD
*Tech Tree of Choices: [http://opensourceecology.org/wiki/Backhoe_pivot_tech_tree_of_choices Backhoe Pivot -- Tech Tree of Choices]
**Used Coggle to develop Tech Tree -- need to work out Coggle integration issues with our wiki
*LibreCAD update: just used pen & paper and cardboard vs LibreCAD--we have two ideas: 1) two controls/valves for increased range of motion, 2) Single valve with less range of motion. Next step is to use prototyping tools to build each and test the ROM.
*Shop clean up -- some worked was done.
*Rob will contact


=Production Rhythm=
=Production Rhythm=
Line 658: Line 475:


=Older Entries - Meeting Notes=
=Older Entries - Meeting Notes=
*[[Daily Product Development Meeting/Notes Oct 21-25]]
*[[Daily Product Development Meeting/Notes Oct 14-20]]
*[[Daily Product Development Meeting/Notes Oct 7-11]]

Latest revision as of 16:22, 18 November 2013

Production Meeting Notes

October 28 - November 3

Nov 18, 2013

  • MH -- Need to install the stove today, Mark will work on siding
  • Trencher -- issue with the plates vs the SketchUp mode, made corrections to the prototype, need to update CAD
  • CNC TT -- Sam is up to speed on CNC TT status;

Oct 31, 2013

Agenda: 1) Ironworker, 2) MH, 3) Infrastructure, 4) Logistics, 5) Documentation, 6) CNC Torch Table, 7) Construction

  • Ironworker - Ironworker has legs; still needs a guide installed on the table--99% built; still need to update all of the documentation; upload pictures for legs and build documentation instructions; going to cut tubing today
  • MH -- Working on Dozuki after lunch; meeting with Dan Overby to discuss energy modeling;
  • Infrastructure -- still raining, not going to have Jake come out today; Jake was able to remove the bricks around the stove so we can re-install when welding is complete
  • Documentation --
  • CNC TT -- Hardware needs to be updated, but is working now; need to replace one of the motor mounts; wants to create some software for testing; is moving in 3 dimensions now
  • Construction -- MH is the south: Ideal client -- Has land to build it, has the capital to build it (~$15K), has place for attendees to stay/camp, has experience with construction/planning/building, in the south, will dedicate a blog post to this, other logistics: would need to transport our equipment/tractor
  • Other -- 1) Discussed Theodore/Haiti Project with Chris for his SA, 2) Marcin is focused on the Shuttleworth application, 3) Microcar -- Yann is willing to come out in Dec; received Shuttleworth grant; perhaps mid-Jan to Feb will be better -- need to coordinate

Oct 30, 2013

Held mini Production meeting today.

  • Ironworker -- refined precision cutting, putting on feet today, continuing documentation
  • MH -- Mark is getting more wood to complete trim
  • Infrastructure -- Rick is going to come out today to finish digging the drain pipe; Sweiger has the stove, should be done Thurs/Fri
  • Logistics -- Marcin & Dan depart on Fri. They will drive the truck to St Joe and Katie will take them to the airport in her car

Oct 29, 2013

Agenda: 1) Ironworker, 2) MH, 3) Infrastructure, 4) Logistics, 5) Documentation

  • Ironworker -- Sheared 1x8 yesterday; captured documentation of the process -- shear documentation & useage; will be used as part of our workshop infrastructure; need to finish the table, level the table, complete the guide/backstop, and install feet--Dozuki guides will need more work as well; need to capture what was built in Sketchup
  • MH -- need to complete documentation and upload to Dozuki, but this is a lower priority than the Shuttleworth documentation deliverables for the Ironworker and the Backhoe; Mark needs more wood to finish the framing; still has two more days of "finishing" work
  • Infrastructure -- Stove:Sweiger is making the doors, Marcin wants to deliver the entire structure (frame, etc) so they can finish everything--then we will simply need to install it --- Marcin would like to build a second stove for the workshop for this winter; Marcin will call Sweiger so he can explain what work needs to happen with the frame and how to attach the doors; Marcin wants Mark to install the stove once its done; Marcin wants the bricks removed around the stove; Bush hog: Need to contact Gary to get status when he can come out (Katie)
  • Documentation -- MH: He is uploading to Trovebox, reloading them to 900x600 resolution; Marcin would like for the MH to be divided into sub-folders (i.e. foundation, etc--use what is in Dozuki); Marcin wants to meet with Chris & Rob to work sort documentation (meet today at 1pm CDT); Backhoe:We are missing step instructions, etc for what Cory & Leandra did this summer during 6 in 60; need to ID what documentation is outstanding by each module; Marcin would like to focus Wed/Thurs focusing on documentation -- photos, work instructions, & utilize 3D graphics if we don't have photos for instructions
  • Other: Dan is leaving tomorrow @3:35pm, needs a ride

Oct 28, 2013

Agenda: 1) Design Sprint, 2) Ironworker, 3) MH, 4) Infrastructure, 5) Logistics, 6) Documentation

  • Design Sprint Update-- Created a full Dozuki guide for the Ironworker; needs some editing;
    • Applying this model to the Laser Cutter project -- let's do this same model and get people to support the 3-4 day build process while@ Lasersaur; ACTION -- Marcin to develop a schedule & agenda for Lasersaur (Tues, Wed, Thurs); will advertise via the Blog & through the newsletter;
  • Ironworker -- 2/3s re-assembled; switched tubing from 2/3 to 1/2; cutting 1x6s today;
  • MH --

NOTE: meeting interrupted due to HabLab internet going down




Logs

Current Product Development

Backhoe

Backhoe Development Board

Backhoe Problem Statement and Backhoe Pivot ROM Concept

Backhoe Side to Side Pivot Module

Dozuki Docs: Backhoe

Contact the Backhoe Development Team: ose-backhoe-development@googlegroups.com

Ironworker

Ironworker Problem Statement

Ironworker Product Development Board

Product Development Board - Ironworker Frame Module (to integrate the feet)

Product Development Board - Ironworker Hole Punch Element Module

Product Development Board - Ironworker Shear Table Module

Dozuki Docs: Ironworker

LifeTrac 6

LifeTrac 6 Development Board

Dozuki: LifeTrac 6

Microhouse

Chris Reinhart Log

Microhouse Prep / Checklist

Microhouse Prototype Assessment


Production Rhythm

Monday

  • Enterprise Program Review
  • Review Design Sprint Product(s)

Tuesday

  • Logistics
    • Shop Equipment Status
    • Repair Status
    • Supply Status - Long Lead Parts, High Risk Parts
    • Other Logistics Issues

Wednesday

  • Issues & Risks

Thursday

  • Schedule

Older Entries - Meeting Notes