2014 Planning: Difference between revisions
		
		
		
		
		
		Jump to navigation
		Jump to search
		
				
		
		
	
|  (→Links) | |||
| (10 intermediate revisions by the same user not shown) | |||
| Line 1: | Line 1: | ||
| =2014 Infrastructure Buildout Concept= | =2014 Infrastructure Buildout Concept= | ||
| See [[2014  | '''See [[2014 Infrastructure]]''' | ||
| <html><img src="https://docs.google.com/drawings/d/1NylWrlka8yZ8jzY2Hi-vhP6wxqlBCEbpH6z1ZyWtPtQ/pub?w=1000&h=800"></html> | <html><img src="https://docs.google.com/drawings/d/1NylWrlka8yZ8jzY2Hi-vhP6wxqlBCEbpH6z1ZyWtPtQ/pub?w=1000&h=800"></html> | ||
| Line 31: | Line 31: | ||
| See more at [[Project Review]] for OSE's project management techniques. | See more at [[Project Review]] for OSE's project management techniques. | ||
| = | =CEB Press Workshop - April 25-27, 2014= | ||
| '''See [[CEB Press Workshop]].''' | |||
| [ | |||
| =Chris Critical Path= | =Chris Critical Path= | ||
| Line 89: | Line 81: | ||
| =Links= | =Links= | ||
| *[[Critical Path]] | *[[Critical Path]] | ||
| *[[Infrastructure]] | |||
Latest revision as of 16:20, 23 March 2014
2014 Infrastructure Buildout Concept
2014 Calendar
Note: The image is a Google Drawing with hyperlinks to the different events. To access the links, click edit below the image.
See more notes at Calendar.
OSE 6 Month Plan
2014 Critical Path
See more at Project Review for OSE's project management techniques.
CEB Press Workshop - April 25-27, 2014
See CEB Press Workshop.
Chris Critical Path
April MicroHouse Workshop at FeF
Critical Path Diagram/PERT Review
Milestone and Task Review w/ GANTT
2014 Overview
College Tour
Legend: vibrant purple dot is top 25 overall, purple is 25-50. Dark blue is top 25 engineering, and gets lighter down to top 100.
Planning Overview by Chris
Ops