  • Validate Solar Cement Calculations of 5 tons/day for 200kW array
  • Can MIG Casting convert 3D printed parts to steel and aluminum with sub 1 mm resolution?
  • Can a 100kW induction furnace be built for $5k for the power electronics, cooling, and heating coil? Crucible is included.
  • Can cutting gas oxyhydrogen be produced at a cost of $500 per 10kW?
  • Can a welder power supply for MIG be built for $100 for 10kW?
  • Can a 100kW induction furnace produce 2500 lb of 3" ingot feedstock per day?