Gary DeMercurio Log

From Open Source Ecology
Jump to navigation Jump to search

Wednesday Sept 18, 2013

File:PivotWI.odt

  • Completed powercube with ground hug pivot installation.
  • Completed 50% of Bobcat quick attach, some cutting issues with what we received from the CnC shop, a tad too big, will have to grind down tomorrow.
  • Articulating pivot mounts placed and ready for pivot and hyd cyl.
  • Pins cut for bucket.
  • Life track build fell behind today due to lack of wheels/wheel mounts. Had planned on having at least two completed this morning. Almost have one.
  • Need to have wheels/wheel mounts completed by early afternoon.
  • Still waiting for hydraulic schematics to be completed.
  • Shop not being taken care of properly, have created a power point for with examples of what does not adhere to shop rules, and what does.

[File:ShopClean.odp]

Hours worked: 16

Tuesday Sept 17,2013

File:Oldlifetrac.skp

File:Loaderarms.skp

  • Finished the Axle for the power cube. Due to the separation of the pivot plates it made the over all width the exact size of the powercube. Had to make multiple cuts to get it to fit. Could try and account for error but the amount of error varies.
  • Corrected an issue with the loader arm pivoting due to design issue. Need to ensure going forward to use Dozuki for current model and only give admin rights to staff so it doesn't change. Not the first issue for this build.
  • Power cube ready to connect to articulating pivot, then waiting on Wheel mounts to be complete.
  • Basic cab structure complete, waiting on wheel mounts.


Goals for the Week

  • Complete Life track 6

Goal Completion

  • Finished design of tractor.
  • Cut list complete and cut.
  • Work Flow complete.
  • Work instructions complete except for loader arms (took 4 DPV's 2-3 days to complete WI for last life track, I've had to complete these on my own over the last 4 days.) Had to leave out how bolts went in do to time constraints, need to work in how they are placed for next build (to avoid bolt being stuck and not able to remove after construction)*****.
  • Completed more than 50% of the frame in one day.

Hours Worked: 12

Monday Sept 16, 2013

  • Work instructions, found multiple issues with work instruction due to superimposed tubes that were "inside" other that weren't noticed until the model was "blown apart".
  • Rewired the workshop so that it has wi-fi for the build/future.
  • Completed work instructions along with parts list for Cab Module.
  • Helped with co worker with some presentation issue to free them up for tractor duty.
  • Build meeting with DPV's, outlined build instructions, workshop layout, remaining cuts, welds.
  • Tech meeting with Marcin to go over current issues, WIP, hyd schematics, quick connect wheel mounts.
  • Reconfigured the network and "undid" what the tech help person messed up this weekend. Wireless is back to normal. Re-connected the printer to the network as it wasn't working with the configuration that we were left with from the tech help.

File:WorkInstructionsCab.odp

File:WorkInstructionsPowercube.odp

Build:

  • Cab complete / waiting on Wheel mounts
  • Power cube / Basic structure complete
  • Axle for powercube 60% complete, in place and tacked, needs to be fitted to the powercube frame, as of now .5 inch discrepancy.

Work day ended at 3ish am / 18 hour day

Sunday Sept 15, 2013

  • Completed Cab Instructions, 80% complete with all others.
  • Researched adobe homes, found multiple instances of clay bricks set with mortar, 2000+ sqft build in a single day. End result is a permanent structure that is a "real home" utilized real stucco for the outside is some cases, others utilized the brick as it's weatherproof, unlike our current configuration. Great example of what we should be working towards.


Saturday Sept 14, 2013

Continue to work on Work Instructions for cab, loader arms, pivot and power cube as numerous issues creeped into the Work instructions due to design creep. Finished work at 2am - 17 hour day.

Completed cut list.

Had multiple issues with incorrect parts super imposed into the build that caused issues with the cut list.

Friday Sept 13, 2013

Corrected power cube fit issues which made the previous Work Instructions obsolete. Completed the exploded diagram of the Cab and loader arms along with an over all Parts list / cut list for the build.

File:PartsList.skp

ExplodedCab.Jpg

ExplodedLA.jpg

File:Lifetrac6PCRD(2).skp

Thursday Sept 12, 2013

  • Finished up with some design issues concerning the loader arms and cylinders.
  • Completed the work instructions for the power cube
  • Started on the Work Instructions for the Cab module.

Wednesday Sept 11, 2013

  • Completed work instructions for the power cube module
  • Created burn down list for build

Tuesday Sept 10, 2013

Goals for the Week

Finished design of tractor Start cutlist Work Flow

Goal Completion

  • worked on templates / refined Product Lead process
  • material received
  • Helped with Dozuki

Monday Sept 9, 2013

Travel to FeF

Friday Sept 6, 2013

  • Watched more videos for Auto Inventor, good progress but it is very different than what I am used to with Catia. is going to take more time than I have to do what I want with it prior to the tractor build. Ordered a manual that will hopefully make some of the more tedious things easier with shortcuts, just going to take a lot of time getting familiar.
  • looked for some wheels and tires, found some 31" tires that would work, prices between 150-220$ each at multiple locations. was trying to find a rim and tire set, nothing that would fit the tractor that was reasonable.

Thursday Sept 5, 2013

  • Watched 4 hours of video for Auto Inventor to try and familiarize myself. hoping to be able to run some stress analysis as some point. 4 hours + stopping and starting to try and learn the tools, very time consuming but informative.
  • Updates program managers for times
  • Updated program manager to reflect any issues that were behind schedule adding notes to each.
  • Movers came.

Wednesday Sep 4, 2013

  • Continued to work on burn down list of deliverables.
  • Read Lean Start as well as some research to better answer Daniel question about rapid prototyping as well as seeing if it was a process we could institute at OSE. As of now its not, it does have some good information that we could incorporate however when were ready.

Tuesday Sept 3, 2013

Things to do:

Call Honda

Check Bobcat Quick

Tractor BOM

Wheels and tires

Work Instructions

Completed the Relevance section on the Master Dev board, worked on the board most of the day coming up with things RC would be able to help with. Finished a few Dozuki categories, want to add another section for research.


Goals for Week

  • Continue working on templates / Continue refining Product Lead process
  • Build Prep for next week - Ensure material delivered on time. Proper material is received and adequate for build. Order any additional tooling.
  • Help with Dozuki

Goal Completion

  • Get all parts ordered for Life track
  • Complete initial model with hyd basic structure and all systems complete
  • work on burn down plan with templates and web pages for development.



Older Entries