Seed Eco-Home 4 Build Instructions
Finishing
- Interior walls and onward build by CM [1]
Water System
Build upon SH2 as-built - [2]
Working Doc Part 8 - Cabinets
Current work in Nov 2024 in postelection time as fascism increases slightly and the opposition underground swells.
Working Doc Part 7 - Finishing
Working Doc Part 6 - Interior. Wood filler. Flooring.
Working Doc Part 5 - Utilities, Driveway, Heat Pump
From Oct-Dec 2023
Working Doc Part 4 - From Electrical to Hardscape Concept. Module map. PEX + Plumbing vBOM
From June 14 to about October 2023
Working Doc Part 3 - PV Design, Service Entrance, Module Generators, and Plumbing + PEX Subassemblies, Apertures
Also Garage Door, Microcanopy, finish of Trellis.
Working Doc Part 2 - Foundation Skirt, Doors, Trim, Vinyl, Trellis Drop
Also Module 1, water vBOM
Working Doc Part 1 - Garage, Roof, Runners + PV Mounting
Working Doc - Complete to Start of Part 4
More
SH4 Electrical
SH4 Plumbing
Includes rough plumbing dimensions
Working Doc from the Actual Build - XBX Dec 8-20 Working Doc
QC
- Water inlet - pressure test water inlet to 120 PSI. Threads around pressure reducer are problematic in our design - [4]