Seed Eco-Home 4 Build Instructions: Difference between revisions
Jump to navigation
Jump to search
No edit summary |
|||
(39 intermediate revisions by the same user not shown) | |||
Line 1: | Line 1: | ||
{{RightTOC}} | |||
=Finishing= | |||
*Interior walls and onward build by CM [https://docs.google.com/presentation/d/1d59dtRRtNOKcnrv2rCIuU-fS33oeY_8DJFp3kFoVlWY/edit#slide=id.gfdd84a90cc_0_249] | |||
*Cabinets and hinges - [https://docs.google.com/presentation/d/1CAHbxluYhdO_u1tt3ULRwkGvy3aX7yZ7Q4CxTRK-fIk/edit#slide=id.gea5921d753_0_143] | |||
=Water System= | |||
Build upon SH2 as-built - [https://docs.google.com/presentation/d/1lD6Vai6j6UD15B9Wmi7VGKIHyvaln_UIiDmXEKjSldc/edit#slide=id.g254695d2dd3_0_361] | |||
=Working Doc Part 8 - Cabinets= | |||
[https://docs.google.com/presentation/d/1IglMwlvzJzA5S6ePZJcBh-0rtOnXw41Hl-RiOQfvbNk/edit?usp=drivesdk] | |||
Current work in Nov 2024 in postelection time as fascism increases slightly and the opposition underground swells. | |||
=Working Doc Part 7 - Utility Wall, Trim, Paint= | |||
[https://docs.google.com/presentation/d/1s5gIvejTcUfIEs09uzhcOh4ygYemDaVosFLBqeiJIG0/edit#slide=id.g272be4a7526_0_0 edit] | |||
=Working Doc Part 6 - Interior. Wood filler. Flooring.= | |||
<html><iframe src="https://docs.google.com/presentation/d/e/2PACX-1vQhHru8XjOYDoX2R9GupKUmv0Qq1pYf8KToUM4OCDYJlN2GsEYmd7vRqAaO10njc_Pcs6m5666gKjE8/embed?start=false&loop=false&delayms=3000" frameborder="0" width="480" height="389" allowfullscreen="true" mozallowfullscreen="true" webkitallowfullscreen="true"></iframe></html> | |||
[https://docs.google.com/presentation/d/1HqEL-KNTwGVzpZ4IUoZgkKPCX9_1ahXcBzTx9wZc1KY/edit#slide=id.g2a3f54f2241_1_0 edit] | |||
=Working Doc Part 5 - Utilities, Driveway, Heat Pump= | |||
From Oct-Dec 2023 | |||
<html><iframe src="https://docs.google.com/presentation/d/e/2PACX-1vRxHDnP_9VV8rp3VDHV3N-gSQVzk9hAu3V0tdU86mPuv4cIK1eIqXVnjpB9sZaFWwhq0t028TDcDBgm/embed?start=false&loop=false&delayms=3000#slide=id.g2500e52a144_2_0" frameborder="0" width="480" height="389" allowfullscreen="true" mozallowfullscreen="true" webkitallowfullscreen="true"></iframe></html> | |||
[https://docs.google.com/presentation/d/1cUFfIpwk48Y1Wx2ouODzbNYcj-9i6aH1pSIUEUvy9c4/edit#slide=id.g24fc2880dcc_0_123 edit] | |||
=Working Doc Part 4 - Water Supply vBOM. Module map. PEX + Plumbing vBOM. Hardscape. Electrical.= | |||
From June 14 to about October 2023 | |||
<html> <iframe src="https://docs.google.com/presentation/d/e/2PACX-1vTwIraS-Hf0p0QtuWxC2_Yf3zAZRvCr-_qqT3XDB7Zvr5jLQMd9YMkM7Z__0QhMivVNSdJ8lt7rbBr1/embed?start=false&loop=false&delayms=3000#slide=id.g258e9f675d3_0_102" frameborder="0" width="480" height="389" allowfullscreen="true" mozallowfullscreen="true" webkitallowfullscreen="true"></iframe> </html> | |||
[https://docs.google.com/presentation/d/1YF44L9WZ75y9LLAr8AwxbeC-K__OKJVt7FZzvzeQQ6Y/edit#slide=id.g251b8087080_0_362 edit] | |||
=Working Doc Part 3 - PV Design, Service Entrance, Module Generators, and Plumbing + PEX Subassemblies, Apertures= | |||
Also Garage Door, Microcanopy, finish of Trellis. | |||
<html> <iframe src="https://docs.google.com/presentation/d/e/2PACX-1vTSTLmQEUd2GHU8T-mHxVGbOFIR6Yxu2HCgZqXYbdQY1CuUB4pYoVBM63aj9SGqjXRz02Zm4JDsgZLy/embed?start=false&loop=false&delayms=3000#slide=id.g2415055b18d_3_15" frameborder="0" width="480" height="389" allowfullscreen="true" mozallowfullscreen="true" webkitallowfullscreen="true"></iframe> </html> | |||
[https://docs.google.com/presentation/d/1tdzMFIG1GVURzdCjLESWlnxVFdYFtxkHv2BkSII06eM/edit#slide=id.g251b8087080_0_78 edit] | |||
=Working Doc Part 2 - Foundation Skirt, Doors, Trim, Vinyl, Trellis Drop= | |||
Also Module 1, water vBOM | |||
<html> | |||
<iframe src="https://docs.google.com/presentation/d/e/2PACX-1vQYhUnrOKozT9UPcWg4Xex_cCXL9gyKh54YQ_fmGGg-kCdGVIaQ2zg6BY3Hvad0-rLoYyCtftz_k2Bs/embed?start=false&loop=false&delayms=3000#slide=id.g1f59f8356c1_0_0" frameborder="0" width="480" height="389" allowfullscreen="true" mozallowfullscreen="true" webkitallowfullscreen="true"></iframe> | |||
</html> | |||
[https://docs.google.com/presentation/d/1VgnMRi9HchaZut-AM6nJk28HFXyna09XfRaCudz1AU4/edit#slide=id.g22db16ba519_0_48 edit] | |||
=Working Doc Part 1 - Garage, Roof, Runners + PV Mounting= | |||
<html><iframe src="https://docs.google.com/presentation/d/e/2PACX-1vS0bZqUTPDVB1p6dNzFlFUaf7ir6rhXBFOhAE7Xx9KTT0V63ichwDJvIih-iCrxfzWFu7XmMacJxuLf/embed?start=false&loop=false&delayms=3000#slide=id.g1ee156a4837_0_0" frameborder="0" width="480" height="389" allowfullscreen="true" mozallowfullscreen="true" webkitallowfullscreen="true"></iframe> </html> | |||
[https://docs.google.com/presentation/d/1AU_4ucrdGkkZlsINSIbaOVTh6lG9fWBdCCSyVI1UNQg/edit#slide=id.g20479920c78_0_0 edit] | |||
=Working Doc - Complete to Start of Part 4= | |||
<html> <iframe src="https://docs.google.com/presentation/d/e/2PACX-1vRSTM8eAeLtN6_wvLJtAhAmyoiWkWkwZ2Pzdyx5T4mzNr2axl5UcziYmBW4-MJdG_J-UsvVaQE85vaJ/embed?start=false&loop=false&delayms=3000" frameborder="0" width="480" height="389" allowfullscreen="true" mozallowfullscreen="true" webkitallowfullscreen="true"></iframe> </html> | |||
[https://docs.google.com/presentation/d/190GoVHzn9EBOiRwn0Oj8toZDyr8bd9sYemN50wrJrfg/edit edit] | |||
=Planning - Permit and Foundation= | |||
*See [https://docs.google.com/presentation/d/1ZVCPwdtOtT5dV7ECo1cQ4wyAgfGAwYeQH-Aew-mHs3Y/edit?slide=id.g219f5e64e4c_0_0#slide=id.g219f5e64e4c_0_0] | |||
=More= | |||
*[[Interior Wall Build Process]]. | |||
*[[SEH in 5 Trailer Loads]] | |||
*[[SEH Coordinate System]] | |||
=SH4 Electrical= | =SH4 Electrical= | ||
*[[SEH 4 Electrical]] | *[[SEH 4 Electrical]] | ||
=SH4 Plumbing= | =SH4 Plumbing= | ||
Includes rough plumbing dimensions | |||
*[[SEH 4 Plumbing]] | *[[SEH 4 Plumbing]] | ||
=Working Doc from the Actual Build - XBX Dec 8-20 Working Doc= | =Working Doc from the Actual Build - XBX Dec 8-20 Working Doc= | ||
Line 21: | Line 97: | ||
=More= | =More= | ||
[[Seed Eco-Home 4]] |
Latest revision as of 05:20, 2 April 2025
Finishing
Water System
Build upon SH2 as-built - [3]
Working Doc Part 8 - Cabinets
Current work in Nov 2024 in postelection time as fascism increases slightly and the opposition underground swells.
Working Doc Part 7 - Utility Wall, Trim, Paint
Working Doc Part 6 - Interior. Wood filler. Flooring.
Working Doc Part 5 - Utilities, Driveway, Heat Pump
From Oct-Dec 2023
Working Doc Part 4 - Water Supply vBOM. Module map. PEX + Plumbing vBOM. Hardscape. Electrical.
From June 14 to about October 2023
Working Doc Part 3 - PV Design, Service Entrance, Module Generators, and Plumbing + PEX Subassemblies, Apertures
Also Garage Door, Microcanopy, finish of Trellis.
Working Doc Part 2 - Foundation Skirt, Doors, Trim, Vinyl, Trellis Drop
Also Module 1, water vBOM
Working Doc Part 1 - Garage, Roof, Runners + PV Mounting
Working Doc - Complete to Start of Part 4
Planning - Permit and Foundation
- See [5]
More
SH4 Electrical
SH4 Plumbing
Includes rough plumbing dimensions
Working Doc from the Actual Build - XBX Dec 8-20 Working Doc
QC
- Water inlet - pressure test water inlet to 120 PSI. Threads around pressure reducer are problematic in our design - [6]