Seed Eco-Home 4 Build Instructions: Difference between revisions

From Open Source Ecology
Jump to navigation Jump to search
 
(3 intermediate revisions by the same user not shown)
Line 5: Line 5:
=Finishing=
=Finishing=
*Interior walls and onward build by CM [https://docs.google.com/presentation/d/1d59dtRRtNOKcnrv2rCIuU-fS33oeY_8DJFp3kFoVlWY/edit#slide=id.gfdd84a90cc_0_249]
*Interior walls and onward build by CM [https://docs.google.com/presentation/d/1d59dtRRtNOKcnrv2rCIuU-fS33oeY_8DJFp3kFoVlWY/edit#slide=id.gfdd84a90cc_0_249]
*Cabinets and hinges - [https://docs.google.com/presentation/d/1CAHbxluYhdO_u1tt3ULRwkGvy3aX7yZ7Q4CxTRK-fIk/edit#slide=id.gea5921d753_0_143]


=Water System=
=Water System=
Line 15: Line 16:
Current work in Nov 2024 in postelection time as fascism increases slightly and the opposition underground swells.
Current work in Nov 2024 in postelection time as fascism increases slightly and the opposition underground swells.


=Working Doc Part 7 - Finishing=
=Working Doc Part 7 - Utility Wall, Trim, Paint=


[https://docs.google.com/presentation/d/1s5gIvejTcUfIEs09uzhcOh4ygYemDaVosFLBqeiJIG0/edit#slide=id.g272be4a7526_0_0 edit]
[https://docs.google.com/presentation/d/1s5gIvejTcUfIEs09uzhcOh4ygYemDaVosFLBqeiJIG0/edit#slide=id.g272be4a7526_0_0 edit]
Line 32: Line 33:
[https://docs.google.com/presentation/d/1cUFfIpwk48Y1Wx2ouODzbNYcj-9i6aH1pSIUEUvy9c4/edit#slide=id.g24fc2880dcc_0_123 edit]
[https://docs.google.com/presentation/d/1cUFfIpwk48Y1Wx2ouODzbNYcj-9i6aH1pSIUEUvy9c4/edit#slide=id.g24fc2880dcc_0_123 edit]


=Working Doc Part 4 - From Electrical to Hardscape Concept. Module map. PEX + Plumbing vBOM=
=Working Doc Part 4 - Water Supply vBOM. Module map. PEX + Plumbing vBOM. Hardscape. Electrical.=


From June 14 to about October 2023
From June 14 to about October 2023
Line 69: Line 70:


[https://docs.google.com/presentation/d/190GoVHzn9EBOiRwn0Oj8toZDyr8bd9sYemN50wrJrfg/edit edit]
[https://docs.google.com/presentation/d/190GoVHzn9EBOiRwn0Oj8toZDyr8bd9sYemN50wrJrfg/edit edit]
=Planning - Permit and Foundation=
*See [https://docs.google.com/presentation/d/1ZVCPwdtOtT5dV7ECo1cQ4wyAgfGAwYeQH-Aew-mHs3Y/edit?slide=id.g219f5e64e4c_0_0#slide=id.g219f5e64e4c_0_0]


=More=
=More=

Latest revision as of 05:20, 2 April 2025


Finishing

  • Interior walls and onward build by CM [1]
  • Cabinets and hinges - [2]

Water System

Build upon SH2 as-built - [3]


Working Doc Part 8 - Cabinets

[4]

Current work in Nov 2024 in postelection time as fascism increases slightly and the opposition underground swells.

Working Doc Part 7 - Utility Wall, Trim, Paint

edit

Working Doc Part 6 - Interior. Wood filler. Flooring.

edit

Working Doc Part 5 - Utilities, Driveway, Heat Pump

From Oct-Dec 2023

edit

Working Doc Part 4 - Water Supply vBOM. Module map. PEX + Plumbing vBOM. Hardscape. Electrical.

From June 14 to about October 2023

edit

Working Doc Part 3 - PV Design, Service Entrance, Module Generators, and Plumbing + PEX Subassemblies, Apertures

Also Garage Door, Microcanopy, finish of Trellis.

edit

Working Doc Part 2 - Foundation Skirt, Doors, Trim, Vinyl, Trellis Drop

Also Module 1, water vBOM

edit

Working Doc Part 1 - Garage, Roof, Runners + PV Mounting

edit

Working Doc - Complete to Start of Part 4

edit

Planning - Permit and Foundation

More


SH4 Electrical

SH4 Plumbing

Includes rough plumbing dimensions

Working Doc from the Actual Build - XBX Dec 8-20 Working Doc

edit

QC

  • Water inlet - pressure test water inlet to 120 PSI. Threads around pressure reducer are problematic in our design - [6]

More

Seed Eco-Home 4