Seed Eco-Home 4 Build Instructions: Difference between revisions
Jump to navigation
Jump to search
Line 10: | Line 10: | ||
=Working Doc Part 6 - Interior= | =Working Doc Part 7 - Finishing= | ||
[https://docs.google.com/presentation/d/1s5gIvejTcUfIEs09uzhcOh4ygYemDaVosFLBqeiJIG0/edit#slide=id.g272be4a7526_0_0 edit] | |||
=Working Doc Part 6 - Interior. Wood filler= | |||
<html><iframe src="https://docs.google.com/presentation/d/e/2PACX-1vQhHru8XjOYDoX2R9GupKUmv0Qq1pYf8KToUM4OCDYJlN2GsEYmd7vRqAaO10njc_Pcs6m5666gKjE8/embed?start=false&loop=false&delayms=3000" frameborder="0" width="480" height="389" allowfullscreen="true" mozallowfullscreen="true" webkitallowfullscreen="true"></iframe></html> | <html><iframe src="https://docs.google.com/presentation/d/e/2PACX-1vQhHru8XjOYDoX2R9GupKUmv0Qq1pYf8KToUM4OCDYJlN2GsEYmd7vRqAaO10njc_Pcs6m5666gKjE8/embed?start=false&loop=false&delayms=3000" frameborder="0" width="480" height="389" allowfullscreen="true" mozallowfullscreen="true" webkitallowfullscreen="true"></iframe></html> | ||
[https://docs.google.com/presentation/d/1HqEL-KNTwGVzpZ4IUoZgkKPCX9_1ahXcBzTx9wZc1KY/edit#slide=id.g2a3f54f2241_1_0 edit] | [https://docs.google.com/presentation/d/1HqEL-KNTwGVzpZ4IUoZgkKPCX9_1ahXcBzTx9wZc1KY/edit#slide=id.g2a3f54f2241_1_0 edit] | ||
=Working Doc Part 5 - Utilities, Driveway, Heat Pump= | =Working Doc Part 5 - Utilities, Driveway, Heat Pump= |
Revision as of 21:15, 26 June 2024
Finishing
- Interior walls and onward build by CM [1]
Water System
Build upon SH2 as-built - [2]
Working Doc Part 7 - Finishing
Working Doc Part 6 - Interior. Wood filler
Working Doc Part 5 - Utilities, Driveway, Heat Pump
From Oct-Dec 2023
Working Doc Part 4 - From Electrical to Hardscape Concept. Module map. PEX + Plumbing vBOM
From June 14 to about October 2023
Working Doc Part 3 - PV Design, Service Entrance, Module Generators, and Plumbing + PEX Subassemblies, Apertures
Also Garage Door, Microcanopy, finish of Trellis.
Working Doc Part 2 - Foundation Skirt, Doors, Trim, Vinyl, Trellis Drop
Also Module 1, water vBOM
Working Doc Part 1 - Garage, Roof, Runners + PV Mounting
Working Doc - Complete to Start of Part 4
More
SH4 Electrical
SH4 Plumbing
Includes rough plumbing dimensions
Working Doc from the Actual Build - XBX Dec 8-20 Working Doc
QC
- Water inlet - pressure test water inlet to 120 PSI. Threads around pressure reducer are problematic in our design - [3]