May Production Plan: Difference between revisions
Jump to navigation
Jump to search
Line 11: | Line 11: | ||
See [[Power Cube Documentation]] | See [[Power Cube Documentation]] | ||
'''[[Build Hydraulic Tanks]]''' | '''[[Build Hydraulic Tanks]]''' | ||
Line 26: | Line 24: | ||
'''[[Assemble Power Cube]] | '''[[Assemble Power Cube]] | ||
'''[[Mount Power Cube]]''' | |||
'''[[Test Power Cube on Tractor]]''' | |||
=Tractor Tasks= | =Tractor Tasks= |
Revision as of 00:30, 19 June 2011
Strategy:
- List steps in order of duty – Power Cube to Tractor to CEB press
- Assess capacity required and allocate tasks to 6 fabricators and local shop
- List risks and recovery plans
- Assess daily, before and after workday
- Draw up personnel plan, detailed
Power Cube Tasks
Prepare Electrical System Components
Tractor Tasks
See May Production Run Tractor Tasks
May Production Run New Generator Tasks
May Production Run Generator Tasks