Wed, 18 Sep
Goals for the Week:
Recap from Last Week:
- Establish notional University Tour schedule and ID support materials, etc; send announcement to universities - INW
- ID volunteer position descriptions - categorize by need (primary, secondary, tertiary) and develop primary descriptions - done
Today
- Participated in Production Meeting: Notes
- Corresponded with several people interested in assisting with the Microhouse build
- Questions to OM: Is Chris' team staying at HabLab, camping, hotel? Bed availability? Dates? What is the Microhouse schedule? The schedule in PM is not complete...when are we making forms?
- Corresponded with Jonathan M re: possible university trip to BYU for ED presentation
- Updated DPV Tracker woth Cody H details
- Added Rob B as tentative Microhouse participant to Microhouse Prep / Checklist & DPV Tracker (see Work Day tab)
- Updated OSE Design Sprint page with 21 Sep announcement and 28 Sep Sprint status
Tues, 17 Sep
- Updated calendar & bed logistics for Dan B -- DPV arrival
- LT6 Production notes
- Assisted Katie with gravel research & site plan for parking, roads & walkways
- Slipped and fell on muddy walkway near HabLab -- hurt knee @ ER all afternoon
- Corresponded with several potential collaborators wrt the Microhouse
Mon, 16 Sep
- LifeTrac 6 Production Notes
- Updated PM with latest LT6 status
- Updated OSE Internet & Phone - CenturyLink with Sep 16 call; over to Katie
- Updated OSE Shop Inventory and organized parts from fastenal
- Conducted inventory on receivables; Updated shop inventory
- Updated Travel Reimbursement form [1] for Rob's airport pick up; also requested reimbursement for shop supplies from Home Depot & True Value
- Updated DPV Schedule & integrated into LifeTrac 6 production meeting
- Updated DPV Tracker for Dan B, David J, and James P.
- Created Volunteer Flyer - Local Community
- Assisted with building of cab "warehouse" and beginning of cab assembly
Sun, 14 Sep
- Participated in Production Meeting; cut bonding plates; picked Rob up at the airport; hosted OSE morale event -- attended by Rob, Katie, Gary, James, Emmett & Lucas
Sat, 13 Sep
- Updated Tech Team Culturing Survey and Mail Chimp list with a volunteer's new email address
- Coordinated use of DPV for shop clean up...we need to get ready to build a tractor!
- Cleaned the workshop and prepped material to cut; manually recorded shop inventory (wifi password did not work for OSEtwo); cut 4x4 steel beams
- Purchased ear p;lugs and grease tubes at True Value...picked up more ear plugs, duct tape & limestone at Home Depot Sat evening
- Prepped food and beverage for Potluck dinner on 14 Sep
Fri, 12 Sep
- Lost 45 minutes of work productivity due to internet connectivity issues...cleaned the office and de-cobwebbed the HabLab instead
- Modified Product Development Schedule with bigger font for readability in integrated pages
- Updated Staff and Contractors page on the wiki with current OSE staff members
- Corresponded with several potential volunteers re: Design Sprint participation
- Picked up small generators that were repaired in St Joe
- Continued Academia Tour Plan...coordinating possible BYU speaking engagement in Nov
Thurs, 12 Sep
- Provided input to the blog -- highlighted Emmett's arrival as our first Video Documentation DPV, highlighted current work that Lucas and James are supporting, and included a plug for volunteers. I also asked that a standard statement be included in all future blog posts that inform people how to get involved.
- Provided comments and input to Microhouse Project Pitch Sept 11, 2013 for submission to the foundation. Would like to see these types of documents earlier to provide input from a strategic and community management point of view.
- 11 Sep newsletter has achieved a 20.4% open rate to date; will keep monitoring. Going to slightly change the format for future publications; click rate is high at 4.6% to industry std 3.5%, monitoring...
- Updated Main Page with current Product Development Schedule; updated PDS with current build schedule slippage
- 2013-2014 Academia Tour Plan v.9-12-13
Wed, 11 Sep
- Updated DPV Tracker with Dan B offer
- Coordinating with possible Work Day volunteer: Josh from Kansas City
- MailChimp: Our newsletter for the week of 3 Sep achieved a 22% open rate; up almost 5% from the previous week
- Updated Tech Team Culturing Survey with new sheet that autoupdates and feeds into Mail Chimp listserv with fewer steps
- Researching how to auto feed True Fans list into listserv
- Stopped by GVS Graphics (101 W. Jackson, Maysville MO)to get a quote on embroidery for shirts & screen printing for a table cloth with OSE logo
- Embroidery for shirt: right breast pocket, 3-4" : $90 digitization set up fee (one time fee); $8-10 per shirt (estimate)
- Tablecloth : image approx 12" tall - estimating 3 colors/screen, $15 per screen for set up, $10 for imprint; we could also use older OSE logo (two colors?)
- Updated OSE Facebook page admin access to include all members of Exec Staff
Tues, 10 Sep
Goals for the Week:
- Establish notional University Tour schedule and ID support materials, etc; send announcement to universities
- ID volunteer position descriptions - categorize by need (primary, secondary, tertiary) and develop primary descriptions
Recap from Last Week:
- Complete and begin implementing DPV Recruitment and Management - 2013 Strategic Plan; complete volunteer position descriptions for: 3D Designer, Fabricator, engineer (mech, ag & power electronics), web developer; UPDATE: still INW
- Complete TCM project planning in PM; UPDATE: Done, sending to staff for review
- Recruiting outreach; UPDATE: on-going
Today
- Sourcing tires for LifeTrac6 6 - called Tom's New & Used Tires, (816) 279-2527, 1925 Frederick Ave, Saint Joseph, MO 64501 -- no tires of that size available. He said to call back, they get a new truckload daily. Also checked TSC and found these -- sent to Lucas & Gary
- Updated TCM schedule in PM; exporting for routing / approval of Exec Staff
- Created OSE Staff Internal Routing / Approval Tracker...shared with Exec Staff for feedback/comments
- Tried to export PM to Open Office version of excel, but failed. Will try to export from the pdf so I can post the TCM schedule for review /comment to the staff
- Was able to export to Open Office on my home computer, sent to team via OSE Staff Internal Routing / Approval Tracker
- Stopped at Used tire dealers in Leavenworth; one suggested the size tire we are likely looking for is 235/85R16. Confirming tire size with Lucas & Gary.
- Stopped at Stitch by Stich Custom Embroidery (305 Cherokee, Leavenworth KS, 913-680-0404, POC Sherri Stich) to get quote to have OSE Logo embroidery done -- actual costs can be determined after the logo has been converted / set up in their system; there is a $25 one-time fee for this service; the estimate for a 3-4" logo on the right breast of a polo or button-up shirt is $10-15 if we have under 20 items done. Will look for 2 more quotes.
- Participated in 1:45 min meeting with Exec team and CAF
- Emailed to exec staff sample key duties, tasks & responsibilities document I used on active duty to track recurring tasks (prompted from staff meeting discussion)
- Updated OSE Design Sprint page with correct link to Sep 14th Sprint; updated Events page to include updated Design Sprint info, updated Tractor build info, and expanded Microhouse build schedule
NOTE: Doc appointment today; will work additional 3 hours this evening
Mon, 9 Sep
- Updating Staff Meeting slides
- Received DPV availability from Dan B, sending official offer; DPV app for D. Jensen loaded to wiki, added new potential DPV - Cody Harrison -- all updates in DPV tracker; emailed info to possible DPVs accordingly
- ID'd Primary/secondary/tertiary position descriptions; researched/updated agriculture positions; updated Volunteer Position Descriptions
- Reviewed / updated TCM schedule in PM
- Added Cody Harrison to DPV tracker; coordinated with Cody on next steps
Fri, 6 Sep
- Formatted new OSE laptop -- OSE-02; loaded open office, printer driver, google chrome, formatted bookmarks, etc
- Accepted large FedEx delivery from Surplus Center (took 45 min to unload from truck and place into workshop x 3 people), inventory still needs to be done
- Updated DPV tracker with updated status of DPV (Emmett) and current correspondence for David J; assigned Rob as DPV sponsor for Emmett
- 5 Sep Newsletter stats from Mail Chimp: 17.9% open rate -- up by .4% from last week
- Added Adrian & Colby to distro, deleted Lucas' Berea account info
- Luncheon with Lucas & James S -- great morale booster, said goodbye to James (for now)
- COMPLETED TCM schedule in PM!!!! Now for the execution!
- Hunting down the owner of the Join a Flash Mob database that was on the Wiki Main page...need to migrate contacts to other databases and change ownership of product -- Katie reached out to Aaron for possible intel
Thurs, 5 Sep
- Updated Main Page to redirect collaborators to the Tech Team Culturing Survey and to enroll in our Newsletter Listserv; deleted list for signing up for Flash Mob--migrating Hackathon list to OSE listserv
- Developed first iteration of the weekly OSE newsletter and sent to listserv, to include Design Sprint update
- Linked Mail Chimp list to the Tech Team Culturing Survey so it will auto update (!!!!!!)
- Incorporated button functions to streamline access to Tech Team Culturing Survey & True Fan pages
- Added social media sharing capabilities; need to link to OSE's twitter & Facebook accounts
- Updated DPV Tracker
- Confirmed Emmett's DPV, set appt for informationa telecon; assigned Lucas as his DPV sponsor
- Participated in Staff Meeting--discussed tractor slip schedule and feedback to Dan B to set up dates for October DPV
- Reviewed blog comments and provided information to commentators wrt how to volunteer
Tues, 3 Sep
Goals for the Week:
- Complete and begin implementing DPV Recruitment and Management - 2013 Strategic Plan; complete volunteer position descriptions for: 3D Designer, Fabricator, engineer (mech, ag & power electronics), web developer
- Complete TCM project planning in PM
- Recruiting outreach
Recap from Last Week:
- Implementing DPV Recruitment and Management - 2013 Strategic Plan; complete volunteer position descriptions for: 3D Designer, Fabricator, engineer (mech, ag & power electronics)-- UPDATE: completed plan; implementing strategy; need to finish position descriptions
- Complete & integrate top level schedule into Wiki Landing pages (Wiki Main, Events, Volunteer, DPV pages)-- completed; need to integrate into wiki
Today
- Updated DPV Tracker for Dan B - interview, references update, & recommendation for an offer; drafted offers for 2 DPV apps INW--sent to reporting authority for review/input
- Updating DPV Recruitment and Management - 2013 Strategic Plan
- Updated PM for TCM projects--80% complete
- Responded to numerous volunteer inquiries or DPV reference responses
- Participated in Exec Staff Meeting
- Migrated August log inputs to older entries; started Sept input
- Researched PM for ways to archive old schedules--several options, reported in staff meeting
- Researched ways to segregate MailChimp listservs...ongoing
Mon, 2 Sep
LABOR DAY
- Worked on Mail Chimp newsletter template