Seed Eco-Home 4 Build Instructions
Jump to navigation
Jump to search
Finishing
Water System
Build upon SH2 as-built - [3]
Working Doc Part 8 - Cabinets, Water Heaters, Flooring, Garage Door Installation, Shelves, Final Water and Plumbing
Current work in Nov 2024 in postelection time as fascism increases slightly and the opposition underground swells.
Working Doc Part 7 - Utility Wall, Trim, Paint. Final Wire Routing Map.
Working Doc Part 6 - PV Combiner. DC Disconnect. Transfer Switch. Interior. Wood filler. Flooring.
Working Doc Part 5 - Power Wall. Power Center Finishing. Utilities, Driveway, Heat Pump
From Oct-Dec 2023
Working Doc Part 4 - Water Supply vBOM. Module map. PEX + Plumbing vBOM. Hardscape. Electrical.
From June 14 to about October 2023
Working Doc Part 3 - PV Design, Service Entrance, Module Generators, and Plumbing + PEX Subassemblies, Apertures
Also Garage Door, Microcanopy, finish of Trellis.
Working Doc Part 2 - Foundation Skirt, Doors, Trim, Vinyl, Trellis Drop. Roping technique.
Also Module 1, water vBOM
Working Doc Part 1 - Garage, Roof, Runners + PV Mounting
Working Doc - Complete to Start of Part 4
Planning - Permit and Foundation
- See [5]
More
SH4 Electrical
SH4 Plumbing
Includes rough plumbing dimensions
Working Doc from the Actual Build - XBX Dec 8-20 Working Doc
QC
- Water inlet - pressure test water inlet to 120 PSI. Threads around pressure reducer are problematic in our design - [6]